97 Vt. 97

Udo Peist v. C. M. Richmond et al.

May Term, 1923.

Present: Watson, C. J., Powers, Taylor, and Slack, JJ.

Opinion filed October 3, 1923.

*98Porter, Witters & Longmoore for the plaintiff.

Searles & Graves for the defendant.

Powers, J.

These parties entered into a written contract by the terms of which the plaintiff was to build a house for the defendant for a specified sum, payable in installments as therein provided. For present purposes, it may be stated broadly that one of these installments fell due, and that the defendant wrongfully refused to pay it, and refused to go on under the contract except upon an unwarranted condition. There*99upon, the plaintiff abandoned the work and brought this action of contract using the common counts as his complaint. At the close of the plaintiff’s evidence, the court granted the defendant’s motion for a verdict, and the plaintiff excepted. During the discussion of this motion, the plaintiff expressly declined to seek a recovery on a quantum, meruit basis, and limited his claim to the overdue and unpaid installment; and he adheres to this position in this Court. In these circumstances he cannot maintain his suit.

He concedes that his right to so recover, depends upon the divisibility of the contract. But the contract, being for a finished structure for a gross sum for the work as a whole, and its complete fulfillment being manifestly contemplated by the parties as the basis of their arrangement, is an entire contract, and is not made divisible by the fact that the price for the work is payable in installments. This is sufficiently shown by Creamery Package Mfg. Co. v. Russell, 84 Vt. 80, 78 Atl. 718, 32 L. R. A. (N. S.) 135. There, as here, the contract called for the construction of a completed building for a fixed price payable in installments as the work progressed. “The price for the whole work,” says Chief Judge Rowell, “was $1,500, payable in installments as the work progressed; but the entirety of the contract was not thereby severed and the price apportioned to the different parts of the work, but the whole price remained as the consideration for the complete performance by the defendant,’-’ —the builder. And this is generally so held. Freeman v. Campbell, 22 Ga. 184; Chamberlin v. Borth, 135 Ga. 719, 70 S. E. 569, 35 L. R. A. (N. S.) 1223; Bridgeport v. Scott Co., 94 Conn. 461, 109 Atl. 162; Butterfield v. Byron, 153 Mass. 517, 27 N. E. 667, 12 L. R. A. 571, 25 A. S. R. 654; McConnell v. Corona City Water Co., 149 Cal. 60, 85 Pac. 929, 8 L. R. A. (N. S.) 1171.

The defendant’s failure to make the payment called for by his engagement was a breach of the contract that went to its essence. The situation thus presented to the plaintiff did not, in the respect here involved, differ from what it would have been if the defendant had prevented him from carrying out the contract, as in Derosia v. Ferland, 83 Vt. 372, 76 Atl. 153, 28 L. R. A. (N. S.) 577, 138 A. S. R. 1092, or had put it out of his own power to perform, as in White v. Lumiere North America Co., 79 Vt. 206, 64 Atl. 1121, 6 L. R. A. (N. S.) 807, or had positively and unequivocally refused to perform, as in Temple v. *100Duffy, 96 Vt. 114, 117 Atl. 101, or had refused to perform except upon a condition that he had no right to impose, as in Amsden v. Atwood, 68 Vt. 322, 35 Atl. 311, he, not being in default, could treat the contract as terminated, and without further performance, seek his remedy in the courts. Preble v. Bottom, 27 Vt. 249; Rioux v. Ryegate Bride Co., 72 Vt. 148, 47 Atl. 406; Auer v. Robertson Paper Co., 94 Vt. 473, 111 Atl. 570.

This right of abandonment is, not infrequently, spoken of as the right of rescission. It was so characterized at the argument; which prompts us to suggest, in passing, that technically it differs from the right of rescission in that the contract may still be resorted to by the party not in default for the recovery of his damages. Earnshaw v. Whittemore, 194 Mass. 187, 80 N. E. 520; DeMille Co. v. Casey, 115 Misc. Rep. 646, 189 N. Y. S. 275; Anvil Mining Co. v. Humble, 153 U. S. 540, 38 L. ed. 814, 14 Sup. Ct. 676.

When the plaintiff was ready to bring his suit, he had a choice of remedies: He could sue upon the contract and recover his damages for its breach; or, disregarding the contract, he could sue in general assumpsit for a reasonable compensation for what he had done. Chamberlain v. Scott, 33 Vt. 80. But if one pursues the first-named remedy, he must declare upon the contract, and his damages will be regulated by the contract price. While if one selects the last-named remedy, the contract price does not control his damages, and he recovers quantum meruit. Id. That the declaration must be upon the contract if it is to be made the basis of recovery, is shown, not only by the ease above cited, and the cases therein referred to, but also by Derosia v. Ferland, supra, and cases cited. Whatever may be found to the contrary in Boville v. Dalton Paper Mills, 86 Vt. 305, 85 Atl. 623, is to be disregarded.

Our conclusion that the plaintiff cannot recover the overdue installment is supported by Preble v. Bottom, supra. That case involved a building contract essentially like the one wé have in hand. The plaintiff there agreed to build a house for the defendant for a specified sum, a certain part of which was to be paid by a day named. The defendant failed to make this payment when due, though it was demanded. The plaintiff thereupon abandoned the work and brought suit. The case was tried before auditors, who reported, inter alia, that if the plaintiff was entitled to recover the installment, the balance his due was. *101$78.30; but if he was entitled to recover only in proportion to the work actually done, the balance in his favor was $53.30. It was urged that the plaintiff was entitled to recover according to the agreement, and that any other rule would defeat the contract of the parties and substitute another in its stead. But it was held that the recovery should be for a pro rata compensation according to the contract price, and judgment was given for the last-named sum, — thus denying a recovery of the installment.

The plaintiff insists that the contract was modified by an oral agreement fully carried out by the plaintiff, and that this takes the case out of the rule herein applied. But the modification is referable to and became a part of the original contract and does not, in the respect here involved, affect the rights of the parties.

Judgment affirmed.

Peist v. Richmond
97 Vt. 97

Case Details

Name
Peist v. Richmond
Decision Date
Oct 3, 1923
Citations

97 Vt. 97

Jurisdiction
Vermont

References

Referencing

Nothing yet... Still searching!

Referenced By

Nothing yet... Still searching!