904 F. Supp. 396

In re TMI LITIGATION CONSOLIDATED PROCEEDINGS In re TMI LITIGATION CONSOLIDATED TOURISM CASES Hyland ROGERS, Administratrix of the Estate of James W. Rogers, Plaintiff, v. METROPOLITAN EDISON COMPANY, et al., Defendants.

This Document Relates to All Plaintiffs.

This Document Relates to All Plaintiffs.

Civ. A. Nos. 1:CV-88-1452, 1:CV-88-1551 and 1:CV-88-1558.

United States District Court, M.D. Pennsylvania.

Feb. 18, 1994.

*397Arnold Levin, Philadelphia, PA, Lee C. Swartz, Hepford, Swartz & Morgan, Harrisburg, PA, for Levin-1704 plaintiffs.

Dusan Bratic, Bratic & Portko, Dillsburg, PA, Louis M. Tarasí, Jr., Tarasí & Johnson, P.C., Pittsburgh, PA, for Tarasi-350 plaintiffs.

Peter J. Neeson, LaBrum & Doak, Philadelphia, PA, for Neeson-4 plaintiffs.

Terry S. Hyman, Harrisburg, PA, for Hyman-1 plaintiff.

Gregory H. Knight, Hetrick, Zaleski, Ernico & Pierce, P.C., Harrisburg, PA, for Knight-2 plaintiffs.

Richard P. Haaz, Philadelphia, PA, for Haaz-2 plaintiffs.

Robert S. Mirin, Harrisburg, PA, for Mirin-1 plaintiff.

Gary DeVito, Zarwin, Baum, Resnick & Cohen, P.C., Philadelphia, PA, for Devito-4 plaintiffs.

Shawn A. Bozarth, Harrisburg, PA, for Bozarth-1 plaintiff.

Melville Graham Merlin Walwyn, Melville G.M. Walwyn, P.C., Harrisburg, PA, for Walwyn-3 plaintiffs.

Joseph D. Shein, Philadelphia, PA, for Shein-2 plaintiffs.

Earl L. Harris, Harrisburg, PA, for Harris-3 plaintiffs.

Alfred H. Wilcox, Pepper, Hamilton and Scheetz, Philadelphia, PA, Fred Speaker, Camp Hill, PA, for General Public Utilities Corp., Babcock & Wilcox Co., Pennsylvania Electric Company, Jersey Central Power & Light Co., Metropolitan Edison Company, J. Ray McDermott & Company, McDermott Incorporated, Catalytic, Inc., Raytheon Constructors Inc., Burns & Roe, Inc., Burns and Roe Enterprises, Inc., Dresser Industries, Inc., Dresser Industrial Valve and Instrument Division of Dresser Industries, Inc., defendants.

Charles B. Zwally, Michael D. Reed, Mette, Evans & Woodside, Harrisburg, PA, Augustine V. Cheng, Associate General Counsel, Columbia University, New York City, for George Colbert.

MEMORANDUM

RAMBO, Chief Judge.

Before the court is Defendants’ motion for summary judgment with respect to Plaintiffs’ claims for punitive damages. Briefs have been filed and the motion is ripe for disposition.

Background1

This is not the first time this court has addressed the issue of punitive damages in this case. Early in the history of this litigation, this court concluded that punitive damages were permissible to the extent that funds to pay such damages did not come out of the United States Treasury. In re Three Mile Island Litigation (“TMI I”), 605 F.Supp. 778, 784 (M.D.Pa.1985), rev’d on other grounds sub nom., Kiick v. Metropolitan Edison Co., 784 F.2d 490 (3d Cir.1986).

In TMI I, this court relied heavily on the then-recent decision of the United States Supreme Court in Silkwood v. Kerr-McGee Corp., 464 U.S. 238, 104 S.Ct. 615, 78 L.Ed.2d 443 (1984). In Silkwood, the Supreme Court permitted recovery of punitive damages in a suit brought by an employee of a plutonium processing plant against her employer for radiation-related injuries. The baseline for the Court’s analysis was its observation that “Congress assumed that traditional principles of state tort law would apply with full force unless they were expressly supplanted. Thus, it is [Defendant’s] burden to show that Congress intended to preclude such awards.” Id. at 255, 104 S.Ct. at 625.

The Supreme Court recognized the “tension between the conclusion that safety regulation is the exclusive concern of the federal law and the conclusion that a State may nevertheless award damages based on its *398own law of liability.” Id. at 255, 104 S.Ct. at 625. Regardless of this tension, however, the Court concluded that, “in enacting the Price-Anderson Act, Congress assumed that state-law remedies, in whatever form they might take, were available to those injured by nuclear incidents.” Id.

More important here, the Silkwood court also explicitly rejected an argument by the United States that a punitive damages award would conflict with the federal remedial scheme. Id. at 257, 104 S.Ct. at 626. Conflict preemption is found where:

‘compliance with both federal and state regulations is a physical impossibility,’ Florida Lime and Avocado Growers, Inc. v. Paul, 373 U.S. 132, 142-143 [83 S.Ct. 1210, 1217-1218, 10 L.Ed.2d 248] (1963), or where state law ‘stands as an obstacle to the accomplishment and execution of the full purposes and objectives of Congress.’ Hines v. Davidowitz, 312 U.S. 52, 67 [61 S.Ct. 399, 404, 85 L.Ed. 581] (1941); Felder v. Casey, 487 U.S. 131, 138 [108 S.Ct. 2302, 2306, 101 L.Ed.2d 123] (1988); Perez v. Campbell, 402 U.S. 637, 649 [91 S.Ct. 1704, 1711, 29 L.Ed.2d 233] (1971).

Gade v. National Solid Wastes Management Ass’n, 505 U.S. 88, 98, 112 S.Ct. 2374, 2383, 120 L.Ed.2d 73 (1992) (parallel citations omitted). Thus, in rejecting the government’s conflict preemption argument, the Supreme Court found that “[p]aying both federal fines and state-imposed punitive damages for the same incident would not appear to be physically impossible. Nor does exposure to punitive damages create an obstacle to the accomplishment of Congressional purposes and objectives in enacting the federal nuclear regulatory scheme.” Silkwood, 464 U.S. at 257, 104 S.Ct. at 627.

In the instant motion, Defendants argue that the Price-Anderson Amendments Act of 1988 (“Amendments Act”), 42 U.S.C. § 2011 et seq., as interpreted by the Third Circuit in In re TMI Consolidated Cases II (“TMI II"), 940 F.2d 832 (3d Cir.1991), cert. denied sub nom., Gumby v. General Public Utilities Corp., 503 U.S. 906, 112 S.Ct. 1262, 117 L.Ed.2d 491 (1992), requires the court to reconsider its conclusion in TMI I, to reject the Supreme Court’s analysis in Silkwood and to grant summary judgment in their favor with respect to Plaintiffs’ punitive damage claims. Plaintiffs, on the other hand, assert that this court should follow its previous decision and deny the motion.

Discussion

Initially, Defendants argue that Silk-wood did not dispose of issues relevant to this case because Silkwood was not a Price-Anderson Act case. Defendants are correct that, technically, Silkwood was not within the ambit of the Price-Anderson Act.2 However, in Silkwood, the Supreme Court discussed the Price-Anderson Act at length. During the course of its analysis, the Court clearly considered the provisions of the Act to be part of the relevant “federal remedial scheme” regarding nuclear regulation. For that reason, this court was persuaded in 1985 and still believes that Silkwood is a good barometer of the Court’s likely view of the availability of punitive damages in a Price-Anderson Act case. TMI I, 605 F.Supp. at 782.

More fundamentally, Defendants argue that the Amendments Act requires this court to discard altogether the preemption analysis employed in Silkwood and other pre-Amendments Act cases addressing nuclear power and safety issues. Instead, Defendants argue that this court must “determine whether a specific state rule is or is not ‘consistent with’ the provisions of the Price-Anderson Act.” (Defs.’ Punitive Damages Supp.Br. at 8.)

Regardless of whether this court applies Silkwood’s conflict preemption analysis or the “inconsistency” analysis advocated by Defendants, this court believes that Silkwood counsels a finding that punitive damages are available in this case. If Silkwood’s analysis is still valid, this court has no reason to reconsider its 1985 ruling. Assuming, arguendo, that Silkwood’s approach is no longer proper, this court believes that Silkwood *399still effectively disposes of the arguments raised by Defendants.

Defendants argue in great detail that the award of punitive damages in this case is inconsistent with the overall scheme adopted by Congress in the Price-Anderson Act. However, the Supreme Court addressed essentially this same argument in Silkwood and decided that punitive damages were consistent with applicable federal statutes and regulations. In addressing the government’s conflict preemption argument,3 the Supreme Court explicitly found that “exposure to punitive damages [does not] frustrate any purpose of the federal remedial scheme.” 464 U.S. at 257, 104 S.Ct. at 626 (emphasis added). As discussed above, the Court clearly considered the Price-Anderson Act to be part of the relevant federal remedial scheme. By implication, then, the Silkwood court concluded that punitive damages were not inconsistent with the Price-Anderson Act.4

This was the backdrop against which the Amendments Act was passed. In passing the Act, Congress clearly had an opportunity to overturn the Supreme Court’s pronouncement in Silkwood. In “transforming] ... the entire Price-Anderson landscape ... [w]ith the passage of the Amendments Act,” TMI II, 940 F.2d at 857, Congress did not hesitate to overturn several prior decisions of the Third Circuit with which it disagreed. See 42 U.S.C. § 2014(hh) (providing for federal jurisdiction over suits arising out of all nuclear incidents and reversing Stibitz v. General Pub. Utils. Corp., 746 F.2d 993 (3d Cir.1984), cert. denied, 469 U.S. 1214, 105 S.Ct. 1187, 84 L.Ed.2d 334 (1985); and Kiick v. Metropolitan Edison Co., 784 F.2d 490 (3d Cir.1986)). Yet, despite its substantial revision of the nuclear regulatory scheme, Congress only partially limited Silkwood’s holding.

One provision of the Amendments Act, 42 U.S.C. § 2210(s), expressly prohibits an award of punitive damages “against a person on behalf of whom the United States is obligated to make payments under an agreement of indemnification.” However, while Congress made various provisions of the Amendments Act retroactive, the punitive damages provision was not one of them. See Pub.L. No. 100-408 § 20 (statutory note to 42 U.S.C. § 2014). Thus, that limit does not govern this case. While a statement in the legislative history indicates that Congress did not intend any inference for or against the applicability of punitive damages in other cases be drawn from the provision, see S.Rep. No. 70, 100th Cong., 1st Sess. 27 (1987), U.S.Code Cong. & AdmimNews 1988, p. 1424, the failure of Congress to completely reverse Silk-wood at the very least indicates that Congress did not believe an award of punitive damages in prior cases to be so inconsistent with the purposes of the Act that it must be changed.

Nor does language in TMI II indicate that the Third Circuit perceived punitive damages to be inconsistent with the Act.5 First, the TMI II court discussed Silkwood’s holding regarding punitive damages without giving any indication that it no longer considered its analysis sound.

The court found no conflict in Silkwood, because the award of punitive damages would not impede the congressional goal of promoting nuclear safety. Permitting the states to apply their own nuclear regulatory standards, in the form of the duty owed by nuclear defendants in tort, would, how*400ever, “frustrate the objective of the federal law.”

TMI II, 940 F.2d at 859.

Second, when discussing punitive damages, the TMI II majority noted that the Amendments Act “placed limits on the availability of punitive damages.” 940 F.2d at 854. The court did not interpret the Act as excluding punitive damages altogether. Further, in his concurrence, Judge Seirica went further in noting that “punitive damages remain available when the government is not obligated to make payments under an indemnity agreement.” Id. at 874 n. 6.

Finally, the indemnity agreement cited by the Supreme Court in Silkwood, as evidence that the NRC contemplated the award of punitive damages in Price-Anderson Act cases, see 464 U.S. at 255 and n. 17, 104 S.Ct. at 619 and n. 17, apparently has not changed in the more than five years since the passage of the Amendments Act.

Based on the foregoing, the court concludes that the holding of its prior case remains valid. Accordingly, punitive damages are available in this case to the extent that the funds to pay such damages do not come out of the United States Treasury. An appropriate order will be issued.

Rogers v. Metropolitan Edison Co.
904 F. Supp. 396

Case Details

Name
Rogers v. Metropolitan Edison Co.
Decision Date
Feb 18, 1994
Citations

904 F. Supp. 396

Jurisdiction
United States

References

Referencing

Nothing yet... Still searching!

Referenced By

Nothing yet... Still searching!