80 Colo. 62

No. 11,599.

Brady v. Industrial Commission, et al.

Decided September 13, 1926.

*63Mr. John A. Martin, for plaintiff in error.

Mr. William L. Boatright, Attorney General, Mr. Jean S. Breitenstein, Assistant, Mr. Fred Farrar, Mr. Wendell Stephens, for defendants in error.

En banc.

Mr. Justice Sheaeor

delivered the opinion of the court.

This action was brought by the plaintiff Brady in the district court to review and set aside the findings and award of the defendant, the Industrial Commission, entered against him on October 22, 1925. The defendant, the Industrial Commission, will be referred to here as the “Commission,” and the defendant, the Colorado Fuel & Iron Company, as the “Fuel Company.”

The Commission answered the complaint, and the Fuel Company filed a demurrer thereto. On April 14, 1926, the Commission asked leave to withdraw its answer and join in the demurrer of the Fuel Company, which was granted. The demurrer was then heard and sustained, and the plaintiff electing to stand by his complaint,- judgment was entered for defendant. Plaintiff brings the case here for review. From the record it appears that plaintiff presented to the Commission his application for compensation on account of injuries alleged by him to have been sustained, in the course of his employment, while acting as switchman, coupling a yard engine to a car loaded with steel, and being at the time, as alleged, in the employ of the Colorado-Wyoming Railway Company and the Colorado Fuel & Iron Company.

On September 1, 1925, a hearing was had before a referee of the Commission as to the liability of the Fuel *64Company, the claim against the Colorado-Wyoming Railway Company having theretofore been dismissed, and findings and award entered by the referee against the plaintiff. Thereupon plaintiff petitioned the Commission for' a review of the findings and award of the referee. The referee did not amend or modify the order, but referred the entire case to the Commission.

On October 22, 1925, the Commission made and entered a supplemental award, after having reviewed the entire record and prior proceedings, and denied plaintiff’s claim for compensation. Plaintiff’s complaint did not allege that a petition for review had been filed by plaintiff after the supplemental findings and award had been made by the Commission on October 22.

Plaintiff contends that the court erred in permitting the Commission to withdraw its answer and join in the demurrer of the Fuel Company; also that the court erred in sustaining the demurrer and holding that the complaint should have disclosed that plaintiff filed with the Commission a petition for review of its supplemental award of October 22.

We think the court did not err in either particular. As to the first, the Commission, by its answer, did not waive the question of the court’s jurisdiction of the subject matter of the action, and consequently there was no error in permitting it to join in the demurrer of the Fuel Company. As to the second, the facts disclosed by the record bring this case within the authority of Carlson v. Industrial Commission, 79 Colo. 124, 244 Pac. 68, and that authority is decisive of the instant case.

It is urged, however, that the filing of a petition for review of the order made by the Commission on October 22 would accomplish nothing, and that this case is controlled by Carroll v. Industrial Commission, 69 Colo. 473. We do not think so. The distinction is noted in the Carlson case, supra, and need not be repeated here. At the request of counsel for plaintiff, we have read the entire testimony and the record of proceedings before *65the referee and the Commission. While we cannot, in this proceeding, review the action of the Commission, we might say that if it be a fact, as found by the Commission, that at the time he was injured the claimant was employed by the Colorado & Wyoming Railway Company, an interstate commerce carrier, then the plaintiff could not recover, regardless of the question of the insufficiency of the complaint. The evidence was ample to sustain that finding.

The demurrer was properly sustained, and the judgment should be affirmed.

Brady v. Industrial Commission
80 Colo. 62

Case Details

Name
Brady v. Industrial Commission
Decision Date
Sep 13, 1926
Citations

80 Colo. 62

Jurisdiction
Colorado

References

Referencing

Nothing yet... Still searching!

Referenced By

Nothing yet... Still searching!