117 A.D. 21

Mark M. Nicholls, Appellant, v. American Steel and Wire Company, Respondent.

First Department,

January 11, 1907.

Sale — contract as to shipment of goods construed — measure of damages for failure to deliver — practice—when Appellate Division may direct judgment for plaintiff on special verdict.

In an action for the breach of a contract to deliver goods to he manufactured by the defendant for the plaintiff it appeared that the contract provided that the defendant was to sell four hundred barrels of the. goods at the rate of six to eight barrels per week, the entire quantity to be taken prior to a fixed date. The above portion of the contract was typewritten, and annexed thereto was a piloted specification head'ed “ remarks” wherein it was provided that the purchaser should give the seller specifications for goods'covering shipments not less than ten days before the time of shipment. .

Held, that under said contract defendant was required to ship to plaintiff at least six barrels per week, and that a failure to do so ivas a breach of the contract; That the printed remarks at the end' of the contract referred only to cases where the provisions of the contract contained no specific obligation as to shipment; That as the defendant’s failure to deliver the goods was shown to . have obliged the plaintiff to close its manufacturing plant, the plaintiff was entitled to recover as damage the loss of rent and interest on the capital invested in the factory;

Held, further, that where the court has taken a special verdict which is rendered in favor of the plaintiff and then dismisses the complaint, and there are no exceptions taken by the .defendant which would justify the Appellate Division in ordering a new trial, the Appellate Division on reversing the order dismissing the complaint should direct judgment for the plaintiff on the special verdict.

Clarke and Scott, JJ., dissented.

Appeal by the plaintiff, Hark H. Ficholls, from a judgment of the Supreme Court in favor of the defendant, entered in the office of the clerk of the county of Few York on the 17th day of February, 1905, upon the dismissal of the complaint by direction of the *22court after a trial at the New York Trial Term, a special verdict in favor of the plaintiff having been previously rendered by a jury. .

George T. Sogg, for the appellant.

Joseph P. Cotton, Jr., and George PL. Bartholomew, for the respondent.

Ingraham, J.:

The action was to recover the-damages sustained by the plaintiff in consequence of a breach of a contract for the sale and delivery ,of galvanized broom wire. By the. contract, a copy of which is annexed to the complaint, the defendant sold to the plaintiff 400 barrels No. 21 galvanized broom wire, Shipments to commence upon completion of present contract; to be made at the', rate of 6 to 8 barrels per week, the entire quantity to be taken prior to June 1st, 1902. * * * Each month’s shipment to be treated as a separate and independent contract. * * * Strikes, differences with workmen, accidents to machinery and other contingencies beyond the control of the seller to be sufficient’excuse for any delay in shipment traceable to such cause.” It is alleged that the prior contract was completed August 2, 1901, and that the defendant failed to deliver to the plaintiff during the weeks ending August 9, 16, 23, 30, September 6, 13, 20 "and 27, 1901, six to eight barrels in each week — in all forty-eight to sixty-four barrels- of wire, but delivered only during all of said weeks six barrels of wire, two of which were delivered on August 30,' 1901, and the remaining four barrels on September 10, 1901, and utterly failed to deliver the balance of said forty-two to fifty-eight barrels of wire; that by reason of defendant’s failure to deliver to plaintiff said regular weekly shipments of wire as provided in said contract *. * - * plaintiff was unable to continué his manufacture of flexible tubing, and was compelled to stop the operations of his- factory, and was unable to fill the orders of his customers, and by reason of the premises and defendant’s failure to deliver as aforesaid suffered damages in the sum of Nine thousand seven hundred and fifty dollars ($9,750.00).”

The answer, admitted the making of the contract and that the prior contract was completed on August 2, 1901. It denied the allegations as to the delivery of the wire and alleged that it delivered, *23to the plaintiff two barrels of wire on August twenty-second, four barrels on August thirty-first, six barrels on September twentieth and six barrels on September twenty-fifth, and made other shipments under the contract, and as a separate defense alleged that it was understood between the parties that the plaintiff was to notify the defendant, from time to time, of the amount of wire it desired to be shipped; that the plaintiff did not notify.the defendant that it desired any shipments to be made under the said agreement, otherwise than as such shipments were made by the defendant as particularly set forth, and that the defendant duly complied with the terms of the said agreement and made shipments of the wire therein mentioned as specified by the plaintiff.

The plaintiff testified that at the time the prior contract of October 5, 1900, was about completed, he went to the defendant’s place of business at Cleveland, O., and saw the defendant’s representative ; "that he aslced' the defendant’s representative if the defendant would pay attention and ship me the wire on the new contract without any intermission whatever. He said he would ; ” that at that time there were six barrels more to be" shipped on the. old contract, and that was immediately shipped; that there was no place in the market to get Ho. 21 galvanized wire, except from the defendant; that it had to be made ;for the plaintiff, otherwise he could not get it; that the defendant’s agent was taken over the plaintiff’s factory and shown the plant and was told that the plaintiff could not do anything without the wire; that when the contract of June, 1901, was made the plaintiff told the defendant’s agent that the plaintiff wanted a stated amount in the contract as to what was to be shipped by weekly shipments; that he expected to be very busy; that they had contracts to be delivered a little later, in September and October, one for 150,000 feet of tubing to be delivered before January, 1902, and- specified other orders that he had; that the plaintiff had lost his trade, as he could not fill the orders. There was other proof tending to show that, in consequence of the failure of the defendant to deliver the wires as required by the contract at the rate of from six to eight barrels per week, the plaintiff was unable to manufacture the tubing. Subsequently the court, upon motion of the defendant, struck out the evidence relating to the plaintiff’s business and the order that he had when the con*24tract was executed. The plaintiff then proved the rent paid for his. factory, with his investment in the businessand testified that during the month of August he got. six barrels of wire from the defendant, and. got no wire during the month of September; that, in consequence of the failure of the defendant to deliver the wire as called for by tlie contract, he was Compelled to suspend his business and shut down his factory during the. months of August and September.

The defendant’s representative who made this contract on June 12>: 1901, was' called as. a witness for defendant. He denied the testimony of "the plaintiff as- to the conversation at the-time the' contract was made and testified'that .'the plaintiff told him that lie could not put in any exact Specifications as to the: quantity to be shipped each week, but would let the defendant, know about it later; that lie called at the plaintiff’s -place of business about the twenty-fifth of Jline, when the plaintiff said that he was not ready to place the shipping order and would let defendant'know about further shipments; that about August nineteenth he received an order for Six barrels.of wire to be shipped at onCe, but.that the plaintiff’s representative would give no standing order for shipments. The letter from the plaintiff to the defendant of August 20, 1901, asking why the defendant had not shipped.the plaintiff any wire under the contract, with the'reply of the defendant on August 24, 1901, simply stating that two barrels had been shipped and the balance would follow promptly,, rather sustained the plaintiff’s version of the understanding at the time, this contract was made. If there had been any -such understanding as testified to by the defendant’s witnesses the defendant^in answer to that Inquiry would have stated that as they were not to ship wire until ordered, and no order having been given, nó wire had been, shipped.- '

The court submitted specific questions of fact- to the jury, the first being: “ Did the plaintiff or his son, as his authorized repre-sentative, at some interview or inter vie ws¿ during the month of August, 1901, state to any agent or agents of- -the defendant that specifications or orders or directions as to' shipments desired by plaintiff Under the contract of June the 12th,. 190-1, would thereafter be sent or furnished to the defendant ? ” To this question the .jury answered “ Ho ; ” and that answer, being, sustained by the" evidence, I think justified a verdict for the plaintiff-..

*25The defendant claims that under this contract they were only bound to furnish the wire as specifically ordered by the 'plaintiff. The typewritten portion of the contract, setting forth the understandings, provided that the plaintiff purchased and agreed to receive from the American Steel and Wire Company and the said American Steel and Wire Company agreed to sell to the plaintiff 400 barrels No. 21 galvanized broom wire to be made at "the rate of six to eight barrels per week, the entire quantity to be taken prior to June 1, 1902. Annexed to' this contract were printed specifications headed “Remarks,” and one of these was: “The purchaser Shall give to the seller specifications for goods covering shipments, not less than ten days before time of shipment.” The claim of the defendant is that this printed provision qualifies the obligation to ship weeklyj so that the obligation of the defendant for the weekly shipments only commenced upon the date of the notification by the plaintiff. It will be noticed that the total amount sold was 400 barrels, and of these it was provided that six to eight barrels should be shipped weekly. The express provision as to shipments in the contract would be a specification by the purchaser as to shipments of eight to ten barrels per week. Assuming that eight barrels .per week were shipped for -the balance of the year, from August second to the first of the following June, there would be a considerable amount in addition that the plaintiff was bound to take before the first of June, to make up. the 400 barrels sold, and undoubtedly under this provision, before the plaintiff could place the defendant in default for the additional amount, he would have to give the defendant direction as to shipments. There can be no doubt that if the defendant had gone on shipping to the plaintiff six to eight barrels per week, the plaintiff would have been bound to receive them, even • though he had not ordered them. So, I think, the defendant was required under the contract to ship to the plaintiff at least six barrels of wire per week, and a failure to ship this wire was a breach of the contract. The obligation to ship from six to eight barrels per week was absolute, and-the printed “ remarks ” at the end of the contract would only refer. to a case where the provision of the contract contained no specific obligation as to the shipments, for-where the contract expressly provided when the defendant was to ship the wire sold no further directions were required. . The *26defendant gave testimony tending to show that' after the time at which these shipments were to commence the plaintiff, in substance, requested a delay of the shipment, and that the defendant, acting on that request, had suspended shipments until it received directions from the plaintiff. If this was true, it would justify the defendant in suspending shipments and estop: the plaintiff-from claiming that such a failure to ship was a breach' of the contract; but the jury has found against the defendant upon this question, and their'verdict is controlling. Upon the finding of the jury upon this question submitted to them, therefore,. I think, thé plaintiff was entitled to a verdict for the damages that.he sustained in consequence of the failure of the defendant to deliyer the wire as provided for by- the contract.

- The next question relates to the measure of damages. The plaintiff sought to recover from the defendant the profits upon contracts that it had lost" in consequence of his failure to procure the wire which was necessary for the completion of the contracts. - The court ruled that the plaintiff could.not recover for any loss of profits upon these contracts, and as the plaintiff does not complain of this ruling, it is not necessary to consider the question as to whether this item of damages was proper. The plaintiff, however, alleged in addition to the damages in relation to the contracts with its customers, that by reason-of the defendant’s failure to deliver to the plaintiff the weekly shipments of wire as provided for in said contract, he was unable to continue his manufacture of flexible tubing, and was compelled to stop the operations of his factory; and the Court submitted to the jury the question as to whether the plaintiff was obliged to suspend the -operation of its factory for some' weeks by reason of the fact that he did not receive deli very of the wire f rom the. defendant, and whether the plaintiff sustained damage by reason of such suspénsion of the operation of the factory, to which- they answered, -yes, the jury found that the plaintiff had sustained damages for loss of rent of $624r99 and six per cent interest on the capital invested in this factory of $172.50, making, a total of $749.49.

This, finding, was sustained .by the evidence, and it seems to me that the profits of tlie-business being eliminated, as they had been; by the ruling of the court, the plaintiff was entitled to recover these items of damages which were the direct, loss to him- by the suspen*27sion of his business in consequence of the failure to receive the wire. The evidence showed that if he had been able to continue his business he would have been able to use the building and the machinery in carrying out the contracts for the tubing. By the breach of the contract the plaintiff’s business was suspended, and during tbe period of suspension he was compelled to pay the rent, and lost the interest of the money invested in the factory, and was prevented from making the profits which would usually flow from a successful prosecution of his business. The building and the capital invested were rendered unproductive by reason of the breach by the defend-,, ant of the contract, and it seems to me that plaintiff was at least entitled to be repaid this money that he had been compelled to pay for the property which he was unable to use in the prosecution of his business by reason of the breach of the contract by the defendant.

There are no exceptions taken by the defendant in the case which would justify the court in ordering a new trial, and I think that the judgment entered upon the dismissal of the complaint should be reversed and judgment directed for the plaintiff upon the verdict, with costs in this court and in the court below.

Patterson, P. J., and Laug-hlin, J., concurred; Clarke and Scott, JJ., dissented..

Judgment reversed, with costs, and judgment ordered for plaintiff, with-costs. Order filed.

Nicholls v. American Steel & Wire Co.
117 A.D. 21

Case Details

Name
Nicholls v. American Steel & Wire Co.