134 A.D. 722

Cameron-Hawn Realty Company, Appellant, v. The City of Albany, Respondent.

Third Department,

November 10, 1909.

Contract — municipal corporations — paving contract — construction — defects caused by insufficient plan — engineer’s certificate — condition precedent.

Where a municipal paving contract required that the contractor should keep the pavement in repair for a period of ten years from the date of the acceptance of the work by the city, and in addition keep all the work in good condition and repair for a period of two years, and provided that in case of its failure to do so the city might make the repairs and charge the expense to the contractor or collect it out of a percentage of the contract price retained by the city, the contractor, which has in every respect complied with the plans and specifications prepared, adopted and required by the city, can recover the contract price without repairing the pavement for two years after its acceptance if it appear that the defects therein were caused by the fact that the plan and method of construction specified by the city were insufficient to keep the pavement in repair.

It was impossible for plaintiff to construct the pavement according to the terms of the contract and at the same time produce such a pavement as the defendant required, and, therefore, the reasonable interpretation of the contract is that plaintiff was not to keep the pavement in repair as against the defective plans.

The procuring of a certificate from the city engineer was not a condition precedent to the right of the contractor to maintain an action to recover part of the contract price withheld, for the work having been fully performed it was the duty of the engineer to give such certificate.

Smith, P..J., and Sewell, J., dissented.

Appeal by the plaintiff, the Cameron-Hawn Realty Company, from a judgment of the Supreme Court in favor of the defendant, entered in the office of the clerk of the county of Albany on the 27tli day of February, 1909, upon the report of a referee.

Frederick W. Cameron, for the appellant.

Arthur L. Andrews, for the respondent.

Cochrane, J.:

On the 1st day of April, 190o, the plaintiff entered into a contract with the city of Albany to furnish the material and labor *723necessary to construct an asphalt pavement in one of the streets of said city. Among the conditions of the contract were the following : “ In consideration of the price for laying and maintaining the pavement the contractor must keep the pavement in repair, as hereinafter provided, for a period of ten years from -the date of the acceptance of the work by the city. The maintenance consists in repairs, renewals and furnishing materials necessary to maintain the surface of the street paved by the contractor at all times in a perfect state of uniformity. The uniformity of the street shall be equal to that possessed by it when first accepted, and shall present no marked hollows or projections to admit of water standing on the crown or in the gutters. The surface of the street shall not show any cracks, scaling or other signs of disintegration by the action of the frost and weather, and the pavement shall not show any wear greater than is usual with asphalt block pavements of the best quality under equally heavy traffic.”

In addition to the ten years’ maintenance of the asphalt pavement, all the work herein provided for shall be kept in good condition and repair by the contractor, without notification from the city, for a period of two years from the date of its acceptance by the city, and in case the contractor neglects or refuses to repair the pavement, or other work herein specified, and to restore the same to the grade and to an even and true shape and form of surface, when the same shall be necessary, the Commissioner of Public Works shall have the right to cause said work to be done and charge the expense thereof to the contractor or his sureties ; and the City Treasurer will retain for the period of two years from the date of said acceptance five per cent of the amount due or to become due under the contract, and shall, by such contract, have the right to pay the expense of said repairs and restoration on the certificate of the Commissioner of Public Works out of the five per cent retained by him, or to collect such cost and expenses from such contractor or his sureties.” It was also agreed that the work and materials were to be in strict conformity in every particular with the plans and specifications which were made part of the contract.

This action is brought to recover among, other things five per cent of the amount due under the contract which, according to the provisions thereof above quoted was. retained in behalf of the *724defendant for the purpose of repairing and restoring the pavement, and which amount was stated in the contract to be a guaranty that the work would be kept in proper condition and repair as required by the specifications.

The learned referee found that the plaintiff failed to keep the work done in good condition and repair for the period of two years; that the commissioner of public works of the city of Albany caused the necessary repairs and restoration to be made*; that the expense thereof was $3,161.75 which was paid by the defendant, and that the amount due to the defendant after applying the amount retained was $669.96.

The judgment determines that the plaintiff is not entitled to recover the five per cent of its contract price expended by the city in restoring the pavement, and also charges the plaintiff with the additional amount of $669.96 expended by the defendant for that purpose in addition to said five per cent of the contract price retained by defendant.

The learned referee also found as a fact that the plaintiff “ performed the work and furnished the materials in accordance with the conditions thereof and performed all the conditions thereof on its part to be performed ; that during the time of the performance of said work the defendant inspected the materials furnished and the work performed, and on or about the 4th day of December, 1905, accepted the work in said contract mentioned as having been done in accordance therewith and the materials as having been furnished as provided for in said contract.” It also appears that the contract was prepared by' the city and the work was done under its superintendence and in full conformity with its plans and specifications.

The fact is that the city specified a defective plan and method of construction which, although fully and fairly executed, was insufficient to keep the pavement in repair, and the question for determination is whether the plaintiff can recover its contract price without repairing the pavement for two years after its acceptance by the city, although the plaintiff has in every respect complied with the plans and specifications adopted and required by the city.

In MacKnight Flintic Stone Co. v. Mayor (160 N. Y. 72) the plaintiff contracted to make a boiler room watertight in the manner and under the conditions prescribed in specifications provided by the *725city, and also agreed to turn over the work guaranteed absolutely water and damp-proof for five years from the date of the acceptance of the work. The plaintiff conformed to the plans and specifications, but the boiler room proved not to be watertight. The court held that the guaranty of the plaintiff applied to its own work and material, but' not to the defective plan of the defendant and that plaintiff could recover. It is stated in the opinion : It would not be reasonable to hold the parties to have intended that the plaintiff was to do a great deal of work and furnish a large quantity of materials according to the specifications of the defendant and under the direction of its officers with no right to vary from the materials or construction specified, and yet get no pay for it unless it produced a certain result, without very plain language to that effect, which we do not find in the instrument before us, although it is elaborate in form and embraces the most minute details. Parties might make such an agreement, but if the language used admitted of a different construction the courts would be apt to adopt it and thus avoid the conclusion that an impossible result was intended. The fault of the defendant’s plan should not prevent the plaintiff from recovering payment for good work done and good materials furnished precisely as the defendant required. The reasonable construction of the covenant under consideration is that the plaintiff should furnish the materials and do the work according to the plan and specifications, and thus make the floors water tight so far as the plan and specifications would permit.”

That case seems to be applicable here and if applicable a reversal of this judgment must follow. As indicated in that case if the plaintiff had executed a plan of its own resulting in a proper and sufficient pavement it would not have been a performance of its contract because it was bound hand and foot to the plan of the defendant. It had no discretion as to the material to be used or the manner in which the work should be done. It was an impossibility for the defendant to construct the pavement according to the terms of the contract and at the same time produce such a pavement as the defendant required. The reasonable interpretation of the contract, therefore, is that plaintiff was not to keep the pavement in repair as against the defective plan provided by defendant.

The case cited also disposes of the contention that the certificate *726of the city engineer was a condition precedent to the right of plaintiff to maintain this action. It was his duty to give such certificate and his refusal to do so was unreasonable.

The judgment should be reversed on the law and facts, the referee discharged and a new trial granted, with costs to the appellant to abide the event.

All concurred, except Smith, P. J., and Sewell, J., dissenting.

Judgment reversed on law and facts, referee discharged and new trial granted, with costs to appellant to abide event.

Cameron-Hawn Realty Co. v. City of Albany
134 A.D. 722

Case Details

Name
Cameron-Hawn Realty Co. v. City of Albany
Decision Date
Nov 10, 1909
Citations

134 A.D. 722

Jurisdiction
New York

References

Referencing

Nothing yet... Still searching!

Referenced By

Nothing yet... Still searching!