61 Mich. App. 443

SHELBY TOWNSHIP v BLOOMSTRAND

(Docket No. 20497.)

Decided May 29, 1975.

Roy W Rogensues, for plaintiff.

Stavoe & Deegan, for defendants.

Before: R. B. Burns, P. J. and M. J. Kelly and O’Hara,* JJ.

M. J. Kelly, J.

On April 3, 1969, the Shelby Township Clerk issued defendants a building permit "pending installation of sprinkler system and exit lights (Fire Marshall request)”. In September of 1969, a fire damaged the subject building. Before he would approve the issuance of a second building permit, the fire marshal insisted on a *444written guarantee from defendants that a fire-prevention sprinkler system would be installed. A letter guaranteeing installation of a sprinkler system was sent to the fire marshal by defendants on October 21, 1969. A second building permit was issued on November 11, 1969.

Defendants failed to install the sprinklers. After extrajudicial attempts to resolve the problem proved fruitless, plaintiff brought suit seeking judicial enforcement of the "guarantee”. From an order granting the requested relief, defendants appeal.

We have carefully examined the claims of evidentiary error. The township ordinance was properly pleaded and introduced into evidence. MCLA 600.2116; MSA 27A.2116; GCR 1963, 112.7. No reversible error resulted from the introduction of the October 21, 1969 letter, since defendant admits writing the letter and conceded the nature of its contents.

The trial court did not err in requiring defendants to install the sprinkler system. Plaintiff properly pleaded a contract claim and the relief ordered was appropriate.

At trial, defendants argued that the township was not authorized by ordinance to demand the installation of sprinklers in their building. Since plaintiff failed to show authorization, defendants argue, the trial judge erred in not finding that the consent of defendants was unlawfully obtained. If the evidence did reveal the actions of the township to be illegal, defendants would prevail. Beachlawn Building Corp v City of St Clair Shores, 370 Mich 128; 121 NW2d 427 (1963). Since no evidence directly on point was introduced, the decisional question is: who bore the burden of introducing evidence of whether the township was authorized to demand the installation of sprinklers.

*445The letter written by defendants manifests their apparent voluntary consent to erect the sprinklers in exchange for the license. Despite this, they claim that in reality they did not voluntarily consent. We find persuasive the reasoning of Hutchinson v Poyer, 78 Mich 337, 340; 44 NW 327 (1889):

"It is an elementary principle that he who impugns a transaction as fraudulent which may or may not be so is not sustained by his own assertion alone in case he is disputed, but has the burden on him to make his allegation good by independent evidence; for he who alleges that a transaction was fraudulent must prove it.”

Defendants failed to present evidence in support of their claim that plaintiff was unauthorized to require fire prevention mechanisms in the building. Since defendants failed to prove their duress defense, the trial judge properly rejected it.

Affirmed. Costs to plaintiff.

Shelby Township v. Bloomstrand
61 Mich. App. 443

Case Details

Name
Shelby Township v. Bloomstrand
Decision Date
May 29, 1975
Citations

61 Mich. App. 443

Jurisdiction
Michigan

References

Referencing

Nothing yet... Still searching!

Referenced By

Nothing yet... Still searching!