713 F. Supp. 2d 849

Gerard J. KEATING, Frank R. Krejci, Jane Krejci, Timothy Peterson, Linda Peterson, Daryl Butterfield, Makala Butterfield, and Janet A. Keating, each individually and on behalf of all persons similarly situated, Plaintiffs, v. NEBRASKA PUBLIC POWER DISTRICT, Nebraska Department of Natural Resources, Dennis L. Rasmussen, Mary A. Harding, Larry A. Linstrom, Darrell J. Nelson, Edward J. Schrock, Ken L. Schmieding, Gary G. Thompson, Larry G. Kuncl, Wayne E. Boyd, Virgil L. Froehlich, Ronald W. Larsen, Brian Dunnigan, and Does 1-100, each in their official capacities, Defendants.

No. 7:07CV5011.

United States District Court, D. Nebraska.

May 12, 2010.

*850Boyd W. Strope, James D. Gotschall, Strope, Gotschall Law Firm, O’Neill, NE, Frank A. Taylor, Julie H. Firestone, Scott G. Knudson, Thomas A. Larson, Briggs, Morgan Law Firm, Minneapolis, MN, Keith A. Harvat, Lieben, Whitted Law Firm, Omaha, NE, Terrance O. Waite, Waite, Mcwha Law Firm, North Platte, NE, William G. Campbell, Campbell Law Firm, Ely, MN, for Plaintiffs.

Kelly R. Hoffschneider, Patricia L. Vannoy, Stephen D. Mossman, Mattson, Ricketts Law Firm, Justin D. Lavene, Marcus A. Powers, Attorney General’s Office, Lincoln, NE, for Defendants.

MEMORANDUM OPINION

LYLE E. STROM, Senior District Judge.

I. INTRODUCTION

This matter is before the Court for ruling on the cross-motions for summary *851judgment (Filing Nos. 147, 150 & 153) the parties1 filed pursuant to the Court’s December 17, 2009, order (Filing No. 146). On April 13, 2009, the United States Court of Appeals for the Eighth Circuit remanded the case to this Court for further consideration of the plaintiffs’ procedural due process claim (Filing No. 125). Keating v. Neb. Pub. Power Dist., 562 F.3d 923, 930 (8th Cir.2009). The parties have filed numerous briefs (Filing Nos. 148, 151, 154,2 159, 161, 163, 168, 171, 173 & 175) and evidentiary submissions (Filing Nos. 149, 152, 155, 160, 162, 164, 172, 174 & 176). On April 23, 2010, the Court held a hearing in connection with the cross-motions. Upon reviewing the motions, briefs, evidentiary submissions, and oral arguments of the parties, the Court finds the plaintiffs’ motion for summary judgment should be denied, and NPPD’s and DNR’s motions for summary judgment should be granted.

II. GENERAL PRINCIPLES OF NEBRASKA SURFACE WATER LAW

Although not directly implicated in the plaintiffs’ procedural due process claim, the Court will discuss some general principles of Nebraska surface water law to aid in understanding how the parties’ appropriation permits relate to each other. Since 1895, Nebraska has utilized the doctrine of prior appropriation for the administration of surface water, such as the confined surface water flowing through the Niobrara River. Keating, 562 F.3d at 925; Richard S. Harnsberger & Norman W. Thomson, Nebraska Water Law & Administration 10, 70 (1984). Under the prior appropriation system, DNR is the agency responsible for administering surface water in Nebraska. See generally Neb.Rev. Stat. §§ 61-201 to 61-219.

As pertinent to this case, there are two types of rights recognized by Nebraska’s prior appropriation doctrine: appropriation rights and preference rights. In re 2007 Administration of Appropriations of Waters of the Niobrara River, 278 Neb. 137, 139, 768 N.W.2d 420, 422 (2009) [hereinafter Bond ]. An appropriation right is a right to divert unappropriated surface water for a beneficial use. Neb.Rev.Stat. § 46-204; Bond, 278 Neb. at 139, 768 N.W.2d at 423. Each appropriator’s appropriation right receives a priority date, which is the date an applicant files an appropriation permit application with DNR. Neb.Rev.Stat. § 46-205; Northport Irr. Dist. v. Jess, 215 Neb. 152, 158, 337 N.W.2d 733, 738 (1983). The priority date of a permit is important because it is used to determine which appropriators have priority in times of water scarcity, as the appropriator “first in time is first in right.” *852Neb.Rev.Stat. § 46-203. An appropriator with the earlier in time priority date is the “senior appropriator,” and the appropriator with the later in time priority date is the “junior appropriator.” Bond, 278 Neb. at 139, 768 N.W.2d at 423. In times of water scarcity, the senior appropriator has the right to continue diverting water against a junior-upstream appropriator. See id. In effect, junior-upstream appropriators must allow sufficient water to pass their diversion head-gates to fulfill the entire appropriation allotments of senior-downstream appropriators. In the course of administering surface water, DNR allows water appropriators to issue a “call” for surface water if the flow of surface water at the appropriator’s diversion point is insufficient to fulfill the appropriator’s permitted diversion rate (Affidavit of Michael Thompson (“Thompson Affidavit”), Filing No. 152-3, ¶ 2).

To illustrate, assume there are two appropriators who are permitted by DNR to divert water from the same stream, one having a priority date of December 31, 2009 (the “2009 appropriator”) and one having a priority date of January 1, 2010 (the “2010 appropriator”). Further assume the 2009 appropriator is located downstream from the 2010 appropriator. If flow levels in the stream fall to such a level that the 2009 appropriator is not receiving its full appropriation from the stream, the 2009 appropriator may place a call with DNR requesting the 2010 appropriator cease diverting water until stream levels return to a level sufficient to fulfill the 2009 appropriator’s allotment.

Although an appropriator may have superior appropriation rights, a junior appropriator may have a senior preference right over a senior appropriator. In times of water scarcity, Nebraska law gives superi- or preference rights to certain uses of surface water regardless of appropriation dates. See Neb. Const, art. XV, § 6; Neb. Rev.Stat. §§ 46-204, 70-668; Bond, 278 Neb. at 139, 768 N.W.2d at 423. For example, appropriators using water for domestic purposes have preference over appropriators using water for any other purpose. Id. And appropriators using water for agricultural purposes have preference over appropriators using water for manufacturing or power purposes. Id. Thus, continuing the example, assuming the 2010 appropriator uses water for agricultural purposes and the 2009 appropriator uses water for power purposes, the 2010 appropriator would have a superior preference right to the 2009 appropriator.

Having a superior preference right, however, does not give a junior appropriator unfettered access to water. “An appropriator having a superior preference right, but a junior appropriation right, can use the water to the detriment of a senior appropriator having an inferior preference right. But the junior appropriator must pay just compensation to the senior appropriator.” Bond, 278 Neb. at 140, 768 N.W.2d at 423. Again, under the example, even though the 2009 appropriator has a senior appropriation right compared with the 2010 appropriator, the 2010 appropriator may nonetheless exercise its senior preference right if it justly compensates the 2009 appropriator.

In exercising a senior preference right, a junior appropriator may either agree with the senior appropriator on an amount constituting just compensation and enter a subordination agreement or, if no agreement is made, a junior appropriator may commence a condemnation proceeding in a county court to determine the amount of compensation. Neb.Rev.Stat. § 70-672; Bond, 278 Neb. at 140, 768 N.W.2d at 423. Once the subordination agreement is in place or the condemnation proceeding has resolved, DNR cannot issue closing notices to the junior appropriator for the period of *853time agreed or contained in the condemnation award. Bond, 278 Neb. at 140, 768 N.W.2d at 424.

III. BACKGROUND

A. Substantive Facts

As stated supra, DNR is the state agency responsible for administering surface water in Nebraska (DNR’s Opening Brief (“DNR OB”), Filing No. 151, ¶ 1). NPPD, a political subdivision of the State of Nebraska, owns and operates Spencer Dam located on the Niobrara River in northern Nebraska. NPPD holds three surface water appropriation permits issued to it or a predecessor institution by DNR or a predecessor agency (See Plaintiffs’ Opening Brief (“POB”), Filing No. 168, ¶ 42). These three permits are: A-359-R, priority date of September 12, 1896 for 35 cubic feet per second (“c.f.s.”); A-1725, priority date of October 30, 1923 for 1450 c.f.s.; and A-3574, priority date of June 8, 1942 for 550 c.f.s. (NPPD’s Opening Brief (“NPPD OB”), Filing No. 148, ¶ 1; POB ¶¶ 43 & 45; DNR OB ¶ 8; see also Thompson Affidavit, Exhibit H (permit documents)). These permits allow NPPD to appropriate a total of 2035 c.f.s. for the operation of the Spencer Dam (NPPD OB ¶ 2).3

The plaintiffs are farmers and ranchers owning or renting land in the Niobrara Watershed (POB ¶ 1). The Keatings own 6700 acres in Holt County, Nebraska and hold two surface water appropriation permits: A-14604, priority date of December 22, 1976 for 1.83 c.f.s.; and A-16012, priority date of October 26, 1981 for 1.78 e.f.s.4 (POB ¶¶ 2, 16; NPPD OB ¶ 4; see also Thompson Affidavit, Exhibit B (permit documents)). The Butterfields rent the Keatings’ land for raising crops and livestock (POB ¶ 3). The Krejcis own 14,539 acres in Holt County and also hold two surface water appropriation permits: A-13320, priority date of December 17, 1974 for 25.8 c.f.s.; and A-17988, priority date of June 18, 2001 for 1.89 c.f.s. (POB ¶¶4, 18; NPPD OB ¶ 4; see also Thompson Affidavit, Exhibit C (permit documents)). The Petersons rent the Krejcis’ land for raising crops and livestock (POB ¶ 5). In applying the general principles of Nebraska water law to this case, NPPD is the senior appropriator, and the plaintiffs are junior appropriators, since NPPD’s latest priority date is June 8, 1942, and the plaintiffs’ earliest priority date is December 17, 1974.5

The first surface water appropriation permit certificates DNR issued to the Keatings and the Krejcis state in their text:

This is to certify that the foregoing Application Number [Permit Number] for a *854permit to divert water for irrigation has been examined, and it is hereby approved subject to the following limitations and conditions, viz:
9th. That the prior rights of all persons who, by compliance with the laws of the State of Nebraska, have acquired the right to use the waters of the natural streams of the state must not be interfered with by the use of water under this permit.
11th. The records show that there are periods during some years when the supply of water in [stream name] is not sufficient to meet the requirements of all those having appropriations for its use. The Applicant under this permit is hereby given notice that he may be denied the use of water during times of scarcity.
12th. Section 6, Article XV, Constitution of Nebraska, 1920 and Section 70-668 and 70-669, Reissue Revised Statutes of Nebraska, 1943, govern the use of water, and provide that waters previously appropriated for power purposes may be taken and appropriated for irrigation purposes, upon due and fair compensation therefor; and, inversely they cannot be appropriated arbitrarily for irrigation purposes without just compensation.

(Thompson Affidavit, Exhibit B, at 1 (Permit A-14604); id., Exhibit C, at 1 (Permit A-13320)). For the later-issued permits, DNR sent application approval letters to the Keatings and the Krejeis containing similar language (See id., Exhibit B, at 5-6 (Permit A-16012); id., Exhibit C, at 5-6 (Permit A-17988)).

On March 2, 2007, NPPD placed a continuing call on the Niobrara River for Spencer Dam (DNR OB ¶ 17). Upon an initial investigation, DNR determined the Niobrara’s flow levels were sufficient to satisfy NPPD’s appropriations for Spencer Dam, and therefore took no action to administer the Niobrara for the benefit of NPPD’s appropriation permits (Id.). On March 27, 2007, DNR performed a field investigation, in which it determined NPPD could beneficially use the full amount of water it was entitled to use under its appropriation permits (Id. ¶¶ 19-20). However, during the course of this investigation, DNR determined Niobrara’s flow levels were sufficient to satisfy NPPD’s appropriations, thus obviating the need for administration (Id. ¶ 20.)

Although DNR determined the Niobrara’s flow levels were sufficient as of March 27th to fulfill NPPD’s needs, DNR sent regulating notices to all appropriators upstream of Spencer Dam notifying them of their specific permit allocations and prohibiting them from exceeding those allocations (Affidavit of Brian Dunnigan (“Dunnigan Affidavit”), Filing No. 152-1, ¶ 22 & Exhibit C). The Keatings and the Krejeis both received regulating notices for their appropriation permits (Id., Exhibit C, at 1-2, 4-5). The regulating notices did not provide information regarding the call NPPD had placed (See id.).

In April 2007, the Niobrara’s flow levels began to fall (DNR OB ¶ 23). In response, DNR sent closing notices on May 1, 2007, to appropriators junior to NPPD who diverted water upstream of Spencer Dam6 (Id.). The closing notices stated the appropriator receiving the notice was prohibited from diverting water for the benefit of Spencer Dam until further notice was given (Dunnigan Affidavit, Exhibit D). The Keatings and the Krejeis both re*855ceived closing notices for their appropriation permits (Id.). After issuing the closing notices, DNR continued monitoring flow levels on the Niobrara and eventually-determined flow levels were rising to a level sufficient to satisfy NPPD’s allotment (DNR Reply Brief, Filing No. 173, at 19). Thus, on May 7, 2007, DNR sent opening notices to the junior appropriators who had received closing notices. (Dunnigan Affidavit, Exhibit E). On May 10, 2007, DNR issued a letter to the junior appropriators who had received closing notices discussing why DNR had issued the closing notices for NPPD’s benefit (Dunnigan Affidavit, Exhibit F).

As Nebraska law recognizes preference rights in addition to priority rights, junior appropriators, such as the plaintiffs, who used water from the Niobrara river for agricultural purposes, had a superior preference right to NPPD, which used water for power purposes. Thus, due to the water scarcity in 2007 and junior appropriators’ senior preference right, NPPD undertook negotiations during the summer of 2007 with many junior appropriators in an effort to enter into subordination agreements with the junior appropriators (See Dunnigan Affidavit, Exhibits G & H). While the negotiations were ongoing, NPPD requested DNR delay administration of the Niobrara through August 1, 2007 (Dunnigan Affidavit, Exhibit H). During these negotiations, none of the plaintiffs entered into subordination agreements with NPPD nor instituted a condemnation proceeding.

On August 1, 2007, DNR reinstated closing notices against junior appropriators upstream of Spencer Dam (Dunnigan Affidavit, Exhibit I). The Keatings and the Krejcis again received closing notices (Id.). These closing notices were later lifted between August and October 2007 (Dunnigan Affidavit, Exhibits J & K). Eventually, the Krejcis entered into a subordination agreement with NPPD, but the Keatings did not (DNR OB ¶¶ 32 & 33).

B. Procedural History

The plaintiffs filed this action on May 10, 2007. In their amended complaint (Filing No. 60), the plaintiffs brought two claims for relief. First, the plaintiffs alleged DNR and NPPD’s actions violated plaintiffs’ procedural due process rights under the Fourteenth Amendment to the U.S. Constitution, pursuant to 42 U.S.C. § 1983, and sought an injunction to prevent DNR from issuing or enforcing future closing notices (Amended Complaint (“AC”), Filing No. 60, ¶¶ 156-59). Second, the plaintiffs sought a declaratory judgment declaring NPPD’s appropriation permits were abandoned and DNR’s closing notices were issued ultra vires (AC ¶¶ 160— 64).

After DNR and NPPD filed motions to dismiss (Filing Nos. 74 & 83), the Court entered an order on August 1, 2007, 2007 WL 2248054, dismissing the plaintiffs’ procedural due process claim (Order, Filing No. 115, at 2). As this was the plaintiffs’ only federal claim, the Court also dismissed without prejudice the plaintiffs’ pendant state law ultra vires claim (Id. at 4).

The plaintiffs then appealed to the Eighth Circuit, which on April 13, 2009, reversed and remanded the case to this Court for further proceedings. Keating, 562 F.3d at 923, 930. In its opinion, the Eighth Circuit provided the following instructions to the Court:

On remand, the district court must determine if a deprivation of a property right has occurred, ... and if so, whether that right is subject to an exception to the general rule that a predeprivation process is required. If the court should find that predeprivation process is required, then it must consider whether *856the DNR’s declaratory order procedures are constitutionally adequate. After addressing these issues, the district court should proceed, if necessary, with the case.

Id. at 930. The Eighth Circuit also reinstated the state law ultra vires claim. Id.

On remand, the Court stayed the action (Filing No. 129) pending the Nebraska Supreme Court’s ruling in the case of In re 2007 Administration of Appropriations of the Waters of the Niobrara River, 278 Neb. 137, 768 N.W.2d 420 (2009) [hereinafter Bond ], a case arising out of the same circumstances as this case but with different farmers and ranchers as plaintiffs. The Bond case raised the issue of the validity of NPPD’s appropriation permits, but that issue was not before the Supreme Court. The Supreme Court ultimately remanded the Bond case to DNR on July 17, 2009, for adjudication of the validity of NPPD’s appropriation permits. Bond, 278 Neb. at 148, 768 N.W.2d at 428. The parties have informed the Court that DNR anticipates it will hold a hearing on the validity of NPPD’s permits on July 27, 2010 (POB ¶ 107). After the Supreme Court ruled in Bond, this Court ordered (Filing No. 146) the parties to file cross-motions for summary judgment addressing the issues the Eighth Circuit identified in its opinion. After vigorous briefing by the parties and an informative hearing, the Court is ready to rule on the plaintiffs’ procedural due process claim.

IV. SUMMARY JUDGMENT STANDARD

Rule 56(c) of the Federal Rule of Civil Procedure provides “[t]he judgment sought should be rendered if the pleadings, the discovery and disclosure materials on file, and any affidavits show that there is no genuine issue as to any material fact and that the movant is entitled to judgment as a matter of law.” When a case, such as this one, has unresolved issues that are chiefly legal rather than factual, summary judgment is particularly appropriate. Noe v. Henderson, 456 F.3d 868, 869 (8th Cir.2006) (per curiam). If the plaintiff cannot support each essential element of his claim, summary judgment will be granted because a complete failure of proof regarding an essential element necessarily renders other facts immaterial. Celotex Corp. v. Catrett, 477 U.S. 317, 322-23, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986).

V. PROCEDURAL DUE PROCESS CLAIM

The Eighth Circuit instructed the Court to determine whether the plaintiffs’ rights to procedural due process under the Fourteenth Amendment were violated. Keating, 562 F.3d at 930. The Eighth Circuit provided a three-step analysis for the Court to utilize in reviewing the plaintiffs’ procedural due process claim. Id. Initially, the Court must determine whether DNR and NPPD deprived the plaintiffs of a protected property right through the issuance of closing notices. Id. If DNR and NPPD did not deprive the plaintiffs of a protected property right, no further analysis of the plaintiffs’ procedural due process claim is needed, as the plaintiffs would have failed to prove an essential element of their claim. See id. In resolving this initial issue the Court must address two questions. First, do the plaintiffs have a property right? And if so, second, was this property right deprived?

A. The Plaintiffs’ Property Right

The parties generally agree the plaintiffs hold some property rights. However, the parties do not agree about the scope of these property rights. For example, the plaintiffs argue they have a “protected property interest in the exercise of them permits and the use of their water” (POB at 20). Conversely, DNR argues the *857plaintiffs “can only claim a limited property interest in the priority of their appropriation permits, which only bestow the right to use surface water subject to the higher priority of all senior appropriators.” DNR OB at 23. Similarly, NPPD argues the plaintiffs’ property right “is a limited right to use the water” and is not a “ ‘claim of entitlement’ to water in the Niobrara without regard for the circumstances.” NPPD OB at 11, 12. Accordingly, the Court must define the scope of the plaintiffs’ property rights under their surface water appropriation permits.

For the purposes of procedural due process, plaintiffs have a property right in disputed property when they have a “legitimate claim of entitlement.” Barnes v. City of Omaha, 574 F.3d 1003, 1006 (8th Cir.2009) (quoting Bd. of Regents of State Colls, v. Roth, 408 U.S. 564, 577, 92 S.Ct. 2701, 33 L.Ed.2d 548 (1972)). Although federal constitutional law determines whether the due process clause protects a property right, property rights are not created by the Constitution. Town of Castle Rock v. Gonzales, 545 U.S. 748, 756-57, 125 S.Ct. 2796, 162 L.Ed.2d 658 (2005); Habhab v. Hon, 536 F.3d 963, 968 (8th Cir.2008). Rather, property rights originate from “state law or some other independent source sufficient to establish mutually explicit understandings of entitlement.” Barnes, 574 F.3d at 1006 (internal quotations omitted); see also Gonzales, 545 U.S. at 756, 125 S.Ct. 2796. Thus, the Court looks to Nebraska law and other independent sources to define the plaintiffs’ property rights.

As a threshold matter, it is clear the plaintiffs do not hold any right in the waters of the Niobrara River prior to capture. The Nebraska Supreme Court has repeatedly stated the holder of a surface water appropriation permit does not acquire ownership of stream water prior to capture, as that water is public property. See, e.g., Spear T Ranch, Inc. v. Knaub, 269 Neb. 177, 185, 691 N.W.2d 116, 127 (2005) (“A right to appropriate surface water however, is not an ownership of property. Instead, the water is viewed as a public want....”); Northport, 215 Neb. at 158, 337 N.W.2d at 738 (“The corpus of running water in a natural stream is not the subject of private ownership. ‘Such water is classed with light and the air in the atmosphere. It is publici juris or belongs to the public....’”); Frenchman Valley Irr. Dist. v. Smith, 167 Neb. 78, 99, 91 N.W.2d 415, 428 (1958) (“The appropriator of water of a stream does not acquire ownership of such water.”). Thus, the Court must reject any contention by the plaintiffs that they have a legitimate claim of entitlement, or property right, in the water flowing through the Niobrara River prior to capture.

Permit holders, however, acquire some property rights under Nebraska law through obtaining surface water appropriation permits. Loup River, 142 Neb. at 152-53, 5 N.W.2d at 247-48; see also Enterprise Irr. Dist. v. Willis, 135 Neb. 827, 284 N.W. 326, 329 (1939) (collecting cases announcing that a public water appropriator obtains a vested property right). The holder of a surface water appropriation permit acquires a right to use surface water within the capacity limits of the stream. Northport, 215 Neb. at 158, 337 N.W.2d at 738; Frenchman, 167 Neb. at 99, 91 N.W.2d at 428.

This right to use, however, is not without limit. The appropriator “takes this right ... subject to the rights of all prior and subsequent appropriators, and he cannot infringe upon their rights and privileges.” Farmers’ Irr. Dist. v. Frank, 72 Neb. 136, 100 N.W. 286, 293 (1904); see Northport, 215 Neb. at 159, 337 N.W.2d at 738 (stating prior cases have held “that a landowner does not have an exclusive right *858to use waters to the injury of senior appropriators.”); see also Harnsberger & Thomson, supra, at 113 (“Once priorities are determined by [DNR] they constitute vested rights, and among themselves appropriators have priority according to the dates on their respective appropriations.”). Indeed, the limits of the plaintiffs’ property rights are stated in the text of their permits, which provide: “[T]he prior rights of all persons who, by compliance with the laws of the State of Nebraska, have acquired the right to use the waters of the natural streams of the state must not be interfered with by the use of water under this permit.” In essence, by taking their right of use subject to the rights of other appropriators, permit holders hold a right to their place on the priority list.

In addition to the right to use water, permit holders can also acquire preference rights depending on how the permit holder uses the water. Neb. Const, art. XV, § 6; Neb.Rev.Stat. §§ 46-204, 70-668; Bond, 278 Neb. at 139, 768 N.W.2d at 423; see, e.g., Thompson Affidavit, Exhibit B, at 1 ¶ 12. In this case, the plaintiffs, who use water for agricultural purposes, hold a superior preference right over NPPD, which uses water for power purposes. The plaintiffs could uphold their senior preference right if they justly compensated NPPD by way of a subordination agreement or condemnation proceeding. Bond, 278 Neb. at 140, 768 N.W.2d at 423.

The property rights granted to an appropriator by an appropriation permit are also subject to regulation and supervision by the State of Nebraska by virtue of its police power. In re Water Appropriation Nos. 442A, 161, 162 & 185, 210 Neb. 161, 165-66, 313 N.W.2d 271, 274 (1981) (citing Neb. Const, art. XV, §§ 4, 5) (“As we said in State v. Birdwood Irrigation District, [154 Neb. 52, 55, 46 N.W.2d 884, 887 (1951) ]: The adjudication of the water right gave to [the appropriator] a vested right to the use of the waters appropriated, subject to ... such reasonable regulations subsequently adopted by virtue of the police power of the state.”); State ex rel. Cary v. Cochran, 138 Neb. 163, 292 N.W. 239, 246 (1940); Enterprise, 135 Neb. at 827, 284 N.W. at 330. This view comports with the determination of the Idaho Supreme Court, which recently stated in the context of a Fourteenth Amendment procedural due process challenge to state regulation of surface waters: “A water user has no property interest in being free from the State’s regulation of water distribution in accordance with the prior appropriation doctrine....” In re Idaho Dep’t of Water Res. Amended Final Order Creating Water Dist. No. 170, 148 Idaho 200, 220 P.3d 318, 331 (2009) [hereinafter Thompson ]. Thus, when DNR administers surface water, it is regulating through exercising its police power, and appropriators, like the plaintiffs, receive property rights subject to this regulation.

In sum, the plaintiffs have a protected property right to use surface water from a specific source (i.e., the Niobrara River). In addition, the plaintiffs had a protected property right to exercise their senior preference right if they justly compensate NPPD. However, the plaintiffs’ property rights are limited to the quantity limits of appropriation as specified in their permits, are subject to the rights of other surface water appropriators (i.e., senior appropriators), and are subject to regulation by the state (i.e., administration).

B. Deprivation

The next question is whether DNR and NPPD deprived the plaintiffs of their protected property rights. The answer to this question is clearly no.

First, in a literal sense, the plaintiffs cannot claim a deprivation occurred, as they still retain their appropriation per*859mits and DNR has not sought to revoke those permits, has not sought to change the plaintiffs’ place on the priority list, has not sought to change the amount of water the plaintiffs are entitled to appropriate under their permits, and has not sought to strip the plaintiffs of the ability to exercise their senior preference rights. See Enterprise, 135 Neb. 827, 284 N.W. at 330; see also Thompson, 220 P.3d at 331 (finding no deprivation of a water appropriator’s property rights in violation of procedural due process when the state department of water resources created a new water district, but did not change or subordinate the appropriator’s prior-adjudicated surface water rights). Prior to DNR’s issuance of the closing notices in favor of NPPD’s permits, the Keatings and the Krejcis each held two appropriation permits for specific amounts of water and with certain priority dates. See Thompson Affidavit, Exhibits B & C. After DNR issued the closing notices, the terms of the plaintiffs’ permits did not change and those permits remained in effect. In this respect, the plaintiffs cannot claim they were deprived of property rights.

In addition, the plaintiffs cannot claim a deprivation occurred through DNR’s administration, or regulation, of the Niobrara. The plaintiffs did not have a property right to be free from DNR’s regulation of the prior appropriation system. Since the plaintiffs’ property rights in their permits are subject to regulation by DNR, DNR’s regulation of the plaintiffs’ permits by issuing closing notices cannot act to deprive the plaintiffs of a protected property right. This was the view of the Nebraska Supreme Court in In re Water Appropriations D-887 & A-768, 240 Neb. 337, 482 N.W.2d 11 (1992) [hereinafter Beerline ]. In Beerline, DNR initiated a proceeding against the Beerline Canal Company (“Beerline”) to determine whether to cancel two of Beerline’s surface water appropriation permits. Beerline, 240 Neb. at 338-39, 482 N.W.2d at 13-14. As part of this proceeding, DNR determined Beer-line was impermissibly irrigating two tracts of land with water appropriated under one of its appropriation permits, as these two tracts were not included in the lands granted irrigation rights under the permit. Id. at 339, 482 N.W.2d at 14. Beerline appealed this determination, arguing inter alia that DNR’s determination violated Beerline’s right to procedural due process under the Fourteenth Amendment. Id. at 343, 482 N.W.2d at 16. Upon review, the Supreme Court in Beerline decided DNR’s determination did not deprive Beerline of a protected property right. Id. at 344, 482 N.W.2d at 17. Because Beerline did not have a legitimate claim of entitlement to irrigate lands not covered by their surface water appropriation permits, the court determined DNR could not have deprived Beerline of a protected property right through ordering Beerline to cease irrigating those lands. Id. at 344-45, 482 N.W.2d at 17.

Similar to Beerline, in which Beerline sought to exercise rights in excess of those granted by its permit (i.e., irrigate lands not covered by the permit), the plaintiffs in this case seek to exercise rights in excess of those granted by their permits (i.e., appropriate water notwithstanding NPPD’s senior priority status). In both cases, DNR acted to regulate irrigation practices in order to preserve and enforce the prior appropriation system. Thus, as in Beerline, where the Nebraska Supreme Court determined that DNR did not deprive Beerline of a protected property right through ordering Beerline to cease irrigation of lands not covered by its permit, DNR did not deprive the plaintiffs in this case of a protected property right through issuing closing notices ordering the plaintiffs to cease diverting water in favor of NPPD’s senior adjudicated permits. Stated differently, DNR cannot *860cause a deprivation of the protected property right held by appropriation permit holders when it regulates the appropriation of surface water in order to preserve and enforce the prior appropriation system.7

Because DNR did not deprive the plaintiffs of a protected property right through the issuance of closing notices, procedural due process is not implicated. The plaintiffs have failed to establish an essential element of their procedural due process claim, Celotex Corp., 477 U.S. at 322-23, 106 S.Ct. 2548, and no further analysis of the plaintiffs’ claim is required. See Keating, 562 F.3d at 930. Accordingly, the Court will grant summary judgment in favor of DNR and NPPD on the plaintiffs’ federal claim.

C. State Ultra Vires Claim

The United States Supreme Court has stated that “certainly if the federal claims are dismissed before trial, even though not insubstantial in a jurisdictional sense, the state claims should be dismissed as well.” United Mine Workers v. Gibbs, 383 U.S. 715, 726, 86 S.Ct. 1130, 16 L.Ed.2d 218 (1966). Dismissal of the state claims is not mandatory but is left to the district court’s discretion. Murray v. Wal-Mart, Inc., 874 F.2d 555, 558 (8th Cir.1989). Nothing in this case indicates that the Court should retain jurisdiction over the plaintiffs’ state law ultra vires claim. There has not been a substantial investment of judicial time or resources on the ultra vires issue warranting federal jurisdiction. With the plaintiffs’ procedural due process claim resolved, this action will be dismissed without prejudice as to the plaintiffs’ state law ultra vires claim.

VI. CONCLUSION

The Court will grant summary judgment in favor of DNR and NPPD on the plaintiffs’ procedural due process claim. The Court will also dismiss without prejudice the plaintiffs’ state law ultra vires claim. A separate order will be entered in accordance with this memorandum opinion.

Keating v. Nebraska Public Power District
713 F. Supp. 2d 849

Case Details

Name
Keating v. Nebraska Public Power District
Decision Date
May 12, 2010
Citations

713 F. Supp. 2d 849

Jurisdiction
United States

References

Referencing

Nothing yet... Still searching!

Referenced By

Nothing yet... Still searching!