704 F.2d 1259

CITIES OF CARLISLE AND NEOLA, IOWA, Petitioners, v. FEDERAL ENERGY REGULATORY COMMISSION, Respondent, Iowa Power & Light Company, Intervenor.

No. 82-1146.

United States Court of Appeals, District of Columbia Circuit.

Argued 13 Dec. 1982.

Decided 5 April 1983.

Petition for Review of an Order of the Federal Energy Regulatory Commission.

P. Daniel Bruner, Washington, D.C., with whom Frances E. Francis and Joseph L. Van Eaton, Washington, D.C., were on the brief, for petitioners. Daniel I. Davidson, Washington, D.C., also entered an appearance for petitioners.

Thajauna D. Miller, Atty., F.E.R.C., Washington, D.C., with whom Barbara J. Weller, Deputy Sol., F.E.R.C., Washington, D.C., was on the brief, for respondent.

J. Richard Tiano, Washington, D.C., with whom Lynn Vorbrieh, Des Moines, Iowa, and Patricia M. McEvoy, Washington, D.C., were on the brief, for intervenor, Iowa Power and Light Co.

Before ROBINSON, Chief Judge, WIL-KEY, Circuit Judge, McGOWAN, Senior Circuit Judge.

Opinion for the Court filed by Circuit Judge WILKEY.

WILKEY, Circuit Judge:

Petitioners, the Cities of Carlisle and Neola, Iowa, seek review of the Federal Energy Regulatory Commission (FERC) decision 1 to accept without suspension a rate filing by the Iowa Power and Light Company (IP & L), which supplies electricity to petitioners.2 We find that FERC’s decision in this case is not subject to judicial review, and therefore must dismiss the petition.

I. Facts

Iowa Power and Light submitted its proposed rates in two abbreviated filings made on 8 September 1981.3 The Cities petitioned FERC either to reject the filing on the ground that inadequate cost-of-service data had been provided or to suspend the *1260rate filing for five months.4 The Commission then notified IP & L that additional data would be required before the rates could be accepted for filing; Iowa Power and Light provided additional cost-of-service information on 28 October 1981.5 However, Cities continued to argue that the rate filing should be rejected or suspended pending investigation because the information provided was distorted.6

After considering the submissions of the parties, FERC accepted the proposed rates for filing and terminated the docket in the case without hearing, pursuant to its power under section 205 of the Federal Power Act.7 The Commission found that IP & L had “substantially complie[d]” with the filing requirements, but stated that its acceptance did not constitute approval of the rate.8 After the Commission denied Cities’ application for rehearing,9 Cities filed a petition for review in this court.

II. Analysis

The Federal Power Act10 provides two alternative avenues for FERC consideration of the lawfulness of electric rates and charges. Under section 205, the Commission may begin a proceeding when a new rate schedule is filed with it. In this proceeding, the burden of proof to show the new charges to be reasonable falls upon the utility.11 The Commission is directed to expedite these proceedings.12 Pending an investigation, the Commission may suspend the operation of the schedule for up to five months. If the proceeding is not concluded at the end of the suspension period, the proposed rates go into effect, but the utility may be required to keep accounts so that amounts collected under the new rate schedule can be refunded to consumers.13

The second avenue for review of rates and charges is set out in section 206 of the Federal Power Act.14 This section empowers the Commission to find a rate or charge unreasonable at any time after appropriate hearing. In these hearings, the burden of proof is upon the complaining party, or upon FERC, to show that the challenged rates are unjust or unreasonable.15 Section 206 empowers the Commission to determine the just and reasonable rate, but does not provide for suspension of challenged rates or for refund of payments made under a rate schedule found to be unlawful.16

It is well settled that courts may not review the decision of the Commission to initiate proceedings under section 205.17 A trilogy of cases in this circuit provides the basis for this conclusion. Municipal Light Boards v. Federal Power Commission held *1261that the decision to suspend a rate filing and the length of the suspension period were not subject to judicial review.18 Papago Tribal Utility Authority v. Federal Energy Regulatory Commission held that the decision to accept a rate filing was itself nonreviewable.19 And in Delmarva Power & Light Co. v. Federal Energy Regulatory Commission, where the Commission accepted the rate schedule for filing and suspended the schedule for five months, we declined to review either decision.20

While these cases address attempts to obtain review of the Commission’s decision to accept or to suspend rates, their reasoning is equally applicable to a FERC decision to accept and not to suspend21 In Delmarva Power and Light the court summarized the doctrine of these cases by concluding that the reviewability of an agency decision hinged upon analysis of the “practical function and consequences” of judicial intervention. The three determinative factors in this analysis are “(1) the finality of the order signed, (2) the irreparability of injury to petitioner if review is refused, and (3) the degree to which review will invade a province reserved to agency discretion.”22 In light of the statutory scheme outlined above,23 these factors dictate that we not review the merits of the Commission’s decision in the present case.

First, we note that the Commission’s decision is not a final determination of the lawfulness of the filed rate schedule.24 We do not interpret the Commission’s acceptance of the rate schedule for filing or its refusal to suspend the rates to be a decision that the rates are just and reasonable. Rather, the Commission'here decides only that it will not scrutinize this schedule in a section 205 proceeding. Indeed, the Commission’s order of 23 December 1981 expressly indicated that acceptance “does not constitute approval” of the rates and “is *1262without prejudice to any findings or orders which ... may hereafter be made by the Commission.”25 Neither the Commission’s action below nor our decision here has any effect upon a possible future determination as to the justness and reasonableness of the new rates.26

Second, the Commission’s decision works no irreparable injury on petitioners. It is true that petitioners might suffer various procedural disadvantages in having to proceed via a section 206 rather than a section 205 proceeding. They, rather than the utilities, will bear the burden of proof; and even after successfully meeting this burden, they may be unable to obtain the refunds which would have been available under section 205.27 We cannot hold, however, that these detriments amount to the “irreparable injury” which would prompt us to review an agency decision otherwise unreviewable. Petitioners are “injured” by the Commission’s action only in that they no longer have available to them the more generous remedies granted by section 205. But the statute establishes no right to these more generous provisions. Rather, the plain language of the Act places exclusively within the discretion of the agency the decision whether to institute proceedings under that section.28 Moreover, as with the Interstate Commerce Act, “[t]he statute is silent on what factors should guide the Commission’s decision; ... on the face of the statute there is simply ‘no law to apply’ in determining if the decision is correct.”29 The absence of standards by which to evaluate agency action militates strongly against judicial review.30 Judicial review aimed at protecting petitioners from purported “injury” is thus foreclosed by the structure of the statute as well as its express language.31 To hold that petitioners in this case have been irreparably injured by a purportedly faulty Commission decision would thus grant rights which Congress by plain language declined to create..

Finally, judicial review of the decision not to suspend rates would “create the hazard of forbidden judicial intrusion into the ad*1263ministrative domain.”32 As the Supreme Court has emphasized in reference to the ICC, the power to suspend rates is granted to the agency to preserve its jurisdiction in ratemaking decisions.33 Judicial review of the decision to accept rates would subvert the exercise of this jurisdiction in several ways. First, in reviewing a decision not to suspend, courts must consider the reasonableness and lawfulness of the rates in advance of full administrative consideration. But there remains the possibility that the Commission will consider the substantive lawfulness of the rate schedule through a section 206 proceeding. Review of the decision not to suspend would thus lead to judicial consideration of issues which the Commission might face in the subsequent proceeding.34 Courts would be making the complex and technical rate decisions which Congress determined that the Commission should make in the first instance;35 and different reviewing courts, when reaching diverse results, would engender confusion and inequitable treatment.36

Second, judicial review of the decision not to suspend and not to investigate a challenged rate would enormously interfere with the agency’s control of its own resources and disrupt its day-to-day operation. The decision to investigate under section 205 requires the Commission to conduct expedited proceedings37 and puts great demands on the Commission’s investigatory' resources.38 When deciding to suspend and investigate a rate schedule under section 205 the Commission must consider the wisdom of focusing its resources on this schedule rather than others and to balance the advantages of proceeding under section 205 rather than under section 206. The decisions how to utilize its limited resources and what procedures to follow with regard to timing, burden of proof and remedy are uniquely within the competence of the Commission in the first instance. These decisions not only involve a comparative consideration of the agency’s entire docket and the other filings before it — information not before the court — but also call upon agency expertise in evaluating the complex economic and technical factors underlying a rate filing, expertise which the courts cannot match.

FERC’s decision to accept rates without suspension thus satisfies none of the three criteria for reviewability set out in Delmarva Power and Light. It is not a final determination of the lawfulness of rates; it does not work irreparable injury; and its review by this court would unduly interfere with the exercise of responsibilities properly reserved to the Commission. We therefore hold that the Commission’s decision to accept IP & L’s rates without suspension is not subject to judicial review and direct that the petition for review be

Dismissed.

Cities of Carlisle & Neola v. Federal Energy Regulatory Commission
704 F.2d 1259

Case Details

Name
Cities of Carlisle & Neola v. Federal Energy Regulatory Commission
Decision Date
Apr 5, 1983
Citations

704 F.2d 1259

Jurisdiction
United States

References

Referencing

Nothing yet... Still searching!

Referenced By

Nothing yet... Still searching!