Opinion
This is a companion case to Lewis v. Swan, 49 Conn. App. 669, 716 A.2d 127 (1998). The complaints in both cases bear the same date, and both actions were dismissed in the same proceeding for lack of subject matter jurisdiction pursuant to motions to dismiss filed in each case. In this action, the plaintiff, Walter Lewis, seeks to invalidate the permit issued to the defendant Chelsea G.C.A. Realty Partnership, L.P. (Chelsea), by the Clinton inland wetlands and conservation commission (wetlands commission) and the approval of the site plan granted by the Clinton planning and zoning commission (zoning commission) relating to Chelsea’s construction of the shopping center in Clinton that is the subject of Lewis v. Swan, supra, 669.
The complaint alleges in the first count that both the inland wetlands permit and the site plan approval were defective because they were based on maps that did not accurately depict the boundaries of the wetlands that would be destroyed or disturbed in the construction of the shopping center, that Chelsea knew or should have known of the discrepancies between the actual wetlands as shown on the official map adopted by the wetlands commission in 1986 and the wetlands shown on the maps submitted by Chelsea in support of its applications to both town agencies, and that Chelsea, without a lawful permit as required, is now conducting regulated activities related to construction of the shopping center on land classified as wetlands by the official map of the Clinton wetlands boundaries.1
The second count incoiporates the first count and adds five paragraphs stating that both the zoning commission and the wetlands commission were informed *687at the public hearings relating to Chelsea’s site plan and wetlands permit applications that the wetlands boundaries on the maps of Chelsea’s property were inaccurate and inconsistent with those shown on the official Clinton wetlands map adopted in 1986 pursuant to General Statutes § 22a-42a (b),2 that Chelsea deliberately or with gross negligence insisted that its maps showed the wetlands boundaries accurately and thus misled those town agencies into approving the applications when a substantially larger area of wetlands would be disturbed by the shopping center construction than Chelsea had indicated, and that Chelsea’s construction activities in the wetlands were contrary to law.
The third count incorporates the second count and adds two additional paragraphs alleging that both the zoning commission and the wetlands commission knew or reasonably should have known that Chelsea’s site plan was not consistent with the wetlands boundaries established in 1986 and negligently or wilfully refused *688to comply with the statutes of the state and also the wetlands regulations of the town for changing the established wetlands boundaries.3
Chelsea filed a “motion to dismiss and/or strike” the complaint on the grounds of lack of subject matter jurisdiction and “for failing to state a claim which is legally sufficient.”4 The trial court granted both motions in the same order. In granting Chelsea’s motion to dismiss, the trial court took the same view of the complaint as it had in Lewis v. Swan, supra, 49 Conn. App. 669, that the plaintiff was attempting belatedly to raise issues that he should have raised at the hearings on Chelsea’s applications for approval of its site plan and for a wetlands permit or in an appeal from those determinations and, thus, had failed to exhaust available administrative remedies. The court also concluded that the plaintiff was making a collateral attack on the decisions of the two administrative agencies involved.
I
The characterization of the complaint as a collateral attack on the determinations of the zoning commission and the wetlands commission is incorrect.5 The com*689plaint in this action attacks the orders approving the site plan and the wetlands permit applications directly, not collaterally. The plaintiff claims that neither of those agencies is empowered to change the wetlands boundaries established pursuant to § 22a-42a (b) without first conducting a separate proceeding under that statute for the purpose of revising the original boundaries and that the site plan approval and permit processes do not satisfy the statutory requirements for a wetlands boundary change, particularly its notice provisions.6 The statute provides in part that “[sjuch inland wetland and watercourse boundaries may be from time to time amended, changed or repealed, by majority vote of the inland wetlands agency, after a public hearing in relation thereto is held by the inland wetlands agency, at which parties in interest and citizens shall have an opportunity to be heard and for which notice shall be published in the manner specified in this section. . . .” The plaintiff also relies on provisions of the Clinton inland wetland regulations authorizing the commission to amend regulated area maps “only” in accordance with the procedures of § 22a-42a (b) and requiring any property owner who disputes the designation of any part of his land as a regulated area on the wetlands map to petition the commission to change the designation.7 The complaint may reasonably be construed as *690a challenge to the authority or subject matter jurisdiction of the zoning and the wetlands commissions to revise effectively the boundaries of the wetlands on Chelsea’s land without following the procedures prescribed by § 22a-42a (b) and the town wetlands regulations. The prayer for relief seeks a declaratory judgment that the site plan approval and the wetlands permit are invalid because of the failure to comply with the requirements of § 22a-42a (b) for changing a wetlands boundary and also demands an injunction. The complaint alleges intentional fraud on the part of Chelsea in obtaining the site plan approval and the wetlands permit as an additional ground for invalidating those administrative determinations.
The lack of proper notice of a hearing before a zoning board of appeals has been held to constitute a jurisdictional defect that invalidates the grant of a zoning variance, despite the failure of the plaintiff to appeal therefrom within the time limit. Smith v. F. W. Woolworth Co., 142 Conn. 88, 93-95, 111 A.2d 552 (1955). “Equity can always give relief, in an independent action, to one whose property rights are threatened under a void order of an administrative board.” Id., 93; see also Upjohn Co. v. Zoning Board of Appeals, 224 Conn. 96, 101, 616 A.2d 793 (1992); Carpenter v. Planning & Zoning Commission, 176 Conn. 581, 598, 409 A.2d 1029 (1979); DiCamillo v. Clomiro, 174 Conn. 351, 353-54, 387 A.2d 560 (1978); Moscowitz v. Planning & Zoning Commission, 16 Conn. App. 303, 313, 547 A.2d 569 (1988). Fraud in the procurement of a judgment, when *691it can be established, is another recognized ground for overturning a judgment that would otherwise be final. Miller v. McNamara, 135 Conn. 489, 495-96, 66 A.2d 359 (1949); 2 Restatement (Second), Judgments § 70 (1) (b), comment (c), pp. 180-82 (1982).
We are not obliged to resolve the merits of the allegations of the complaint in reviewing the propriety of granting the motion to dismiss, nor can we do so on the record before us. A motion to dismiss can be granted only for lack of jurisdiction. Practice Book (1998 Rev.) § 10-30. We disagree with the trial court’s conclusion that this case should be dismissed for lack of subject matter jurisdiction because of the failure of the plaintiff to appeal from the administrative determinations that the complaint challenges as invalid. “A court does not truly lack subject matter jurisdiction if it has competence to entertain the action before it.” Monroe v. Monroe, 177 Conn. 173, 185, 413 A.2d 819, appeal dismissed, 444 U.S. 801, 100 S. Ct. 20, 62 L. Ed. 2d 14 (1979). The plaintiffs claim that the challenged administrative orders are void unquestionably falls within the jurisdiction of the superior court, which does not lack competence to decide it. Smith v. F. W. Woolworth Co., supra, 142 Conn. 93-95.
II
The complaint alleges that the plaintiff has standing to bring this action pursuant to General Statutes § 22a-16, which provides in part that “any person . . . may maintain an action in the superior court . . . for declaratory and equitable relief . . . for the protection of the public trust in the air, water and other natural resources of the state from unreasonable pollution, impairment or destruction . . . .” The defendant Chelsea challenges on appeal the sufficiency of the allegations of the complaint to confer standing on the plaintiff and claims that no facts are set forth to indicate that *692Chelsea’s activities are likely to result in “unreasonable pollution” of any natural resource. Although this ground was not raised in the motion to dismiss that was granted, the lack of standing to bring an action may be raised on appeal or at any point in the proceeding.8 Tomlinson v. Board of Education, 226 Conn. 704, 717, 629 A.2d 333 (1993).
A complaint does not sufficiently allege standing by merely reciting the provisions of § 22a-16, but must set forth facts to support an inference that unreasonable pollution, impairment or destruction of a natural resource will probably result from the challenged activities unless remedial measures are taken. Mystic Marinelife Aquarium, Inc. v. Gill, 175 Conn. 483, 502, 400 A.2d 726 (1978). In addition to the invocation of the statute, the plaintiff alleges that (1) in 1986, the wetlands commission established the boundaries of the wetlands area contained within the land on which Chelsea subsequently has been constructing a shopping center, (2) Chelsea’s application for a permit to conduct regulated activities on the wetlands portion of its land indicated that a significantly smaller wetlands area would be affected by the shopping center construction than appears from the official wetlands map, (3) changes in the boundaries of wetlands areas shown on that map can be made only in accordance with § 22a-42a (b), which requires a properly noticed public hearing for that purpose, and (4) Chelsea is currently conducting construction and excavation activities within the boundaries of land classified as wetlands pursuant to statute.
It can hardly be disputed that wetlands constitute a natural resource of this state and that the purpose for enacting § 22a-16 was to prevent their unreasonable “pollution, impairment or destruction.” A motion to *693dismiss “admits all well pleaded facts, the complaint being construed most favorably to the plaintiff.” (Internal quotation marks omitted.) Duguay v. Hopkins, 191 Conn. 222, 227, 464 A.2d 45 (1983). We construe the complaint in this action to allege that Chelsea’s construction activities within the portion of its land designated as wetlands on the map adopted in 1986 are impairing or destroying those wetlands. Any impairment or destruction of such a natural resource would be “unreasonable” if it is occurring unlawfully, as the plaintiff claims, because of the failure to follow the procedures established by § 22a-42a (b), as well as the Clinton inland wetland regulations.
Accordingly, the plaintiff has standing to bring this action pursuant § 22a-16.
III
After granting Chelsea’s motion to dismiss the complaint, the trial court proceeded to grant its motion to strike the complaint for failure of the plaintiff to “state a claim which is legally sufficient.”9 That ruling is flawed for several reasons unrelated to its merits. First, the dismissal of the complaint was a final judgment that effectively terminated proceedings in the trial court. Once the case was dismissed for lack of subject matter jurisdiction, the complaint was no longer before the trial court for the purpose of considering whether it alleged a viable cause of action. Second, the rules of practice provide a plaintiff whose complaint has been stricken an opportunity to amend a pleading deficiency before a final judgment may be rendered. Practice Book (1998 Rev.) § 10-44. This plaintiff, however, was deprived of that opportunity once his complaint was dismissed for lack of jurisdiction. No amendment of the complaint was possible after it had been dismissed. *694Third, there is no final judgment on the motion to strike as contemplated by Practice Book (1998 Rev.) § 10-44 and, therefore, that prerequisite for appellate review has not been satisfied. Accordingly, we must await further proceedings in the trial court relating to the rendition of a final judgment on the motion to strike before we may consider the plaintiffs appeal therefrom.
The judgment is reversed and the case is remanded with direction to deny the motion to dismiss the complaint and for further proceedings with respect to the motion to strike.
In this opinion the other judges concurred.