117 N.Y.S. 770

SCHUMER v. KOHN et al.

(No. 1.)

(Supreme Court, Appellate Term.

June 25, 1909.)

Contracts (§ 321*)—Building Contracts—Nonperformance—Subcontract-’ ors—Owner’s Liability.

Where a building contractor abandoned the work, leaving a substantial part thereof uncompleted, so that the owner was required to expend more than the balance due the contractor to finish the uncompleted portion, the owner was not liable for work and material furnished by a subcontractor.

[Ed. Note.—For other cases, see Contracts, Cent. Dig. § 1508; Dec. Dig. § 321.*]

Appeal from Municipal Court, Borough of Manhattan, Fourth District.

Action by David Schumer against Nathan Kohn, impleaded with others. From a Municipal Court judgment for plaintiff, defendant Kohn appeals.

Reversed, and new trial ordered.

See, also, 111 N. Y. Supp. 728.

Argued before GILDERSLEEVE, P. J., and MacLEAN and SEABURY, JJ.

Samuel S. Koenig, for appellant.

Pollak & Deutsch, for respondent.

PER CURIAM.

The plaintiff, a subcontractor, put up a couple of cornices,- work and material to the value of $20, for- and under a contract with the copartnership, Pototzky & Co., which had a contract with, the defendant for certain alterations on the building at 432 East Fifteenth street belonging to the defendant, who agreed to pay therefor $1,600, payable (1) $400 on the setting of the beams, windows, and frames; (2) $400 on the laying of flooring and covering of roof; (3) $400 on the completion of all the work subject to the owner’s approval; and (4) final payment of $400 on obtaining certificates from the building and tenement house departments showing compliance with their requirements. The third payment was never earned, much less the fourth, as important items of work and of material' undertaken by the contractors were left unperformed and unfurnished. The defendant, besides making the first two payments in full, advanced Pototzky & Co. $300, and also paid one Zwerdling $57 on the partnership account, leaving of the entire contract price $443 unpaid.

The plaintiff herein would have it that because the owner, after Pototzky & Co. had abandoned their job, himself did some work and supplied some material at a cost of $185, making an expenditure by the defendant of $1,342, or $258 less than the contract price, he is bound to pay for the cornices put in under the subcontract with Pototzky &'Co. ’On that the plaintiff has recovered a judgment, which must be reversed, on two. of the items unfinished by the contractor, and which the defendant was obliged to forego or complete himself—38 wardrobes, at $11,. $30,8; .6 mantels, at $7, $42, together amounting to *771$350, which is more than the balance which would have been due the contractors had the work been finished. An effort to sustain the judgment as involving a finding upon a conflict of facts was unsuccessful. Pototzky did testify that he had done all the work; but he and his partner, Wesselkowsky, called by the plaintiff, admitted on cross-examination that, besides failing to supply the wardrobes and mantels mentioned above, they had also failed to put in deafening boards and cleats in the water-closet compartments and flush borders around the new hearths, a new vestibule door, a new front sash, had not finished the woodsheds or furnished pressed crown moldings for the front and vestibule doors. The plaintiff testified to something like an engagement on the part of the defendant to pay him for the cornices. This was not pleaded, was denied, and also practically eliminated on cross-examination. By this failure to show any sum earned and unpaid on the contract, the judgment was unwarranted, and must be reversed.

Judgment reversed, and new trial ordered, with costs to appellant to abide the event.

Schumer v. Kohn
117 N.Y.S. 770

Case Details

Name
Schumer v. Kohn
Decision Date
Jun 25, 1909
Citations

117 N.Y.S. 770

Jurisdiction
New York

References

Referencing

Nothing yet... Still searching!

Referenced By

Nothing yet... Still searching!