644 F. Supp. 1016

Marco MUSCARELLO and Patricia A. Muscarello, Plaintiffs, v. VILLAGE OF HAMPSHIRE, Defendant.

No. 85 C 1996.

United States District Court, N.D. Illinois, E.D.

Oct. 1, 1986.

Jeffrey Lawrence, Elgin, 111., for plaintiffs.

Henry E. Mueller, John B. Murphey, Ancel, Glink, Diamond, Murphy & Cope, P.C., Chicago, 111., Mark Schuster, Strom, Schuster & McCarty, Elgin, III, for defendant.

MEMORANDUM OPINION AND ORDER

SHADUR, District Judge.

Marco Muscarello and his wife Patricia (“Muscarellos”) sue the Village of Hampshire (“Village”) under 42 U.S.C. § 1983 (“Section 1983”), claiming Village took their property:

1. without paying just compensation and
2. without affording them due process in the form of notice and a hearing.

For those claimed Fifth and Fourteenth Amendment violations1 Muscarellos seek:

1. injunctive relief;
2. $1 million in compensatory damages; and
3. $1 million in punitive damages.

Village has moved under Fed.R.Civ.P. (“Rules”) 12(b)(1) and 12(b)(6) to dismiss:

1. this entire action for lack of jurisdiction (that is, as premature) or, if not,
2. Muscarellos’ punitive-damages claim.

For the reasons stated in this memorandum opinion and order, the first-stated motion is granted.2

*1017 Facts 3

Muscarellos own a 113-acre parcel of land (the “Property”) within Village’s corporate boundaries (113). They acquired an interest in the Property under a 1973 land contract and became record titleholders in 1977 (115).

In 1971 Village’s Planning Commission granted Phillips Construction Company (“Phillips”) permission to subdivide a parcel of land (the “Subdivision”) abutting the Property’s western edge (H 6). On February 7, 1974 the Subdivision project was put into receivership, and Village assumed control (117).

One item then requiring completion was the Subdivision’s storm drainage system (id.). Though the watershed did not naturally flow from the Subdivision toward the Property, Village’s plans called for diverting runoff water onto the Property (11118, 10). In May and July 1975 Village’s engineers wrote Village that the drainage system as proposed would create a possible danger of water damage to adjacent land (¶ 9). Nevertheless, Village built a storm sewer from the Subdivision 200 feet into the Property (¶ 10). Resulting storm water flooding has rendered 27 acres of the Property unsuitable for farming and has hindered residential, commercial and agricultural development of the Property as a whole (II12).

Village never told Muscarellos of its plan to build a sewer line on the Property, nor were Muscarellos offered a hearing on the matter before the sewer was built. Village has never offered Muscarellos any compensation for their claimed losses (11 ll).4

Due Process in Governmental “Takings”

Muscarellos begin with the premise the Due Process Clause requires notice and a hearing before Village can deprive them of property. That general rule of predeprivation procedural rights has most recently been stated in Cleveland Board of Education v. Loudermill, 470 U.S. 532, 105 S.Ct. 1487, 1493, 84 L.Ed.2d 494 (1985) (citations omitted, emphasis in original):

An essential principle of due process is that a deprivation of life, liberty, or property “be preceded by notice and an opportunity for hearing appropriate to the nature of the case.” ... We have described “the root requirement” of the Due Process Clause as being “that an individual be given an opportunity for a hearing before he is deprived of any significant property interest.”

But as Loudermill itself points out. (id. n. 7), the rule has various exceptions. There are equally well-established circumstances in which a predeprivation hearing is not required and a postdeprivation hearing opportunity will suffice.

Both sides have canvassed the leading cases requiring or excusing predeprivation hearings and have (of course) drawn opposing conclusions from these cases. Each argument may be stated briefly.

Muscarellos say the controlling question is whether the deprivation is (1) pursuant to a state (or municipal) policy or (2) the result of random, unauthorized behavior. Loudermill (termination of municipal employment) and Logan v. Zimmerman Brush Co., 455 U.S. 422, 102 S.Ct. 1148, 71 L.Ed.2d 265 (1982) (deprivation of state *1018cause of action through official lapse) are— in Muscarellos' view — cases of the former type, while Parratt v. Taylor, 451 U.S. 527, 101 S.Ct. 1908, 68 L.Ed.2d 420 (1981) (negligent destruction of prisoner’s hobby kit)5 and Hudson v. Palmer, 468 U.S. 517, 104 S.Ct. 3194, 82 L.Ed.2d 393 (1984) (random intentional destruction of prisoner’s property) are of the latter. Loudermill-Logan required a predeprivation hearing and Parratt-Hudson did not.

Thus Hudson, 468 U.S. at 532-33, 104 S.Ct. at 3203-04 (footnote omitted) said:

Two terms ago, we affirmed our holding in Parratt in Logan [ ], in the course of holding that postdeprivation remedies do not satisfy due process where a deprivation of property is caused by conduct pursuant to established state procedure, rather than random and unauthorized action.
While Parratt is necessarily limited by its facts to negligent deprivations of property, it is evident ... that its reasoning applies as well to intentional deprivations of property. The underlying rationale of Parratt is that when deprivations of property are effected through random and unauthorized conduct of a state employee, predeprivation procedures are simply “impracticable” since the state cannot know when such deprivations will occur.

Of course Village had to know when it was going to build the Subdivision storm sewer system, so a predeprivation hearing was surely not “impracticable.” Muscarellos urge, then, they are entitled to Louder-mill-Logan protection.

But Village says that is not the relevant distinction for this case. All Muscarellos’ cited cases (Village says) involved deprivations of private property other than for a public use. However, if Muscarellos’ Property was in fact taken, Village says the taking was for a classic example of a public use. Where property is thus taken by the public for the public, Village urges due process does not require a predeprivation hearing.

As against all the cases Muscarellos cite, Village draws sustenance from Williamson County Regional Planning Commission v. Hamilton Bank of Johnson City, 473 U.S. 172, 105 S.Ct. 3108, 3121, 87 L.Ed.2d 126 (1985) (citations and footnotes omitted):

The Fifth Amendment does not proscribe the taking of property; it proscribes the taking of property without just compensation____ Nor does the Fifth Amendment require that just compensation be paid in advance of, or contemporaneously with, the taking; all that is required is that a “ ‘reasonable, certain and adequate provision for obtaining compensation’ ” exist at the time of the taking____ Thus, we have held that taking claims against the Federal Government are premature until the property owner has availed itself of the process provided by the Tucker Act____ Similarly, if a State provides an adequate procedure for seeking just compensation, the property owner cannot claim a violation of the Just Compensation Clause until it has used the procedure and been denied just compensation.

See also Collier v. City of Springdale, 733 F.2d 1311, 1314 (8th Cir.1984) (citation omitted):

If the government chooses to dispense with formal condemnation proceedings prior to the seizure of private property for public use, then the constitution only requires that the property owner be able to bring an inverse condemnation action to compel just compensation____ Thus, it is well settled that a sovereign vested with the power of eminent domain may exercise that power consistent with the constitution without providing prior no*1019tice, hearing or compensation so long as there exists an adequate mechanism for obtaining compensation.

In other words, the Due Process Clause prohibits the taking of property without due process, but that is only the beginning of the inquiry. In response to the controlling question of precisely what “process” is “due,” the Just Compensation Clause expressly permits property to be taken now for a public use, subject only to the later availability of just compensation. Put differently, in the public-taking context “due process” means no more than the provision of just compensation, which may be made post -taking without violating the Due Process Clause. Muscarellos’ procedural due-process analysis, valid as it might be in its proper sphere, is simply inapplicable to eminent-domain cases.

Muscarellos really have nothing to say against Village’s argument. They do not dispute Illinois has adequate procedures for obtaining just compensation after the taking — that has been clear for at least 40 years (see generally Kane v. City of Chicago, 392 Ill. 172, 64 N.E.2d 506 (1946)). They do say an inverse condemnation proceeding cannot fully compensate them for all their investment potential in the Property. That may or may not be so, for the normal meaning of fair market value of property would seem to incorporate its realistic investment potential. But in any case that is not an argument favoring pretaking relief. Williamson County, 105 5. Ct. at 3121-22 teaches that kind of speculative argument renders a Section 1983 lawsuit premature at best.

That public/private dichotomy is what lay behind the famous civics lesson administered by Bi-Metallic Investment Co. v. State Board of Equalization, 239 U.S. 441, 36 S.Ct. 141, 60 L.Ed. 372 (1915). See also Hawaii Housing Authority v. Midkiff, 467 U.S. 229, 239-45, 104 S.Ct. 2321, 3228-32, 81 L.Ed.2d 186 (1984) (discussing scope of Public Use Clause). Payment of fair market value is all the Just Compensation Clause requires (United States v. 50 Acres of Land, 469 U.S. 24, 105 S.Ct. 451, 453, 457, 83 L.Ed.2d 376 (1984)), and — as this opinion has already shown — due-process notions add nothing more.

That disposes of Muscarellos’ claims, for their Just Compensation Clause claim is asserted as a matter of timing only: Village didn’t pay just compensation before it built the sewer. Muscarellos must seek their remedy through state procedures.6 At least until they have done so and failed to obtain satisfaction, their claim is not ripe for decision in a federal court (Williamson, 105 S.Ct. at 3121) and this Court lacks jurisdiction on grounds of prematurity.

Conclusion

Muscarellos’ claim must be addressed in the first instance to the Illinois courts. As Muscarellos have failed to allege a ripe claim for just compensation (and as they cannot claim an independent due-process violation), this action is dismissed as premature — a dismissal for lack of subject-matter jurisdiction.

Muscarello v. Village of Hampshire
644 F. Supp. 1016

Case Details

Name
Muscarello v. Village of Hampshire
Decision Date
Oct 1, 1986
Citations

644 F. Supp. 1016

Jurisdiction
United States

References

Referencing

Nothing yet... Still searching!

Referenced By

Nothing yet... Still searching!