OPINION ANNOUNCING THE JUDGMENT OF THE COURT
The Commonwealth of Pennsylvania, Department of Transportation (PennDOT) challenges a Commonwealth Court Order affirming an award of delay damages to The BOC Group under the Eminent Domain Code, 26 Pa. Stat. §§ 1-101—1-903 (Supp.1997). As explained below, we hold that condemnees may recover damages for delays in payment of special damages under the Eminent Domain Code. The BOC Group, however, is not entitled to delay damages since Penn-DOT never took physical possession of the condemned property and there is no evidence that The BOC Group was deprived of the property’s use. Thus, we reverse.
On April 25, 1984, PennDOT filed a declaration of taking to condemn property owned by the Estate of Julia Rochez and leased by The BOC Group, Inc. Sometime before June 1,1984, The BOC Group vacated the building on the property and left behind machinery, equipment, and other personal property. *442In August of 1988, The BOC Group petitioned for the appointment of a Board of Viewers to determine its damages as a result of the condemnation.1 In October of 1992, after a hearing in May, the Board of Viewers issued a report awarding The BOC Group damages for the loss of its machinery and equipment, delay damages, and an attorney and appraisal fee award. PennDOT appealed the delay damages award.
In May of 1993, the Estate of Rochez, The BOC Group and PennDOT executed a Stipulation of Settlement. PennDOT agreed to pay The BOC Group special damages in the amount of $105,865, representing the fair market value of fixed machinery and equipment on the property on the date of condemnation, and $167,775, representing the fair market value of removable machinery and equipment on the property on the date of condemnation. PennDOT would also pay the attorney and appraisal fee award mandated by statute. The parties agreed to mark the viewers’ petition and appeal of the viewers’ decision settled and discontinued. They decided to litigate whether The BOC Group was entitled to delay damages or interest. PennDOT retained the right to assert all defenses to a delay damages claim.
The BOC Group filed an amended petition for the appointment of a Board of Viewers in November of 1993 to decide if delay damages are recoverable. PennDOT filed preliminary objections to the amended petition. The parties then entered a Stipulation of Facts upon which the trial court would decide the issue. They stipulated in part that PennDOT paid the amounts agreed to in the settlement and that all payments arose under Article VI-A of the Eminent Domain Code on special damages.
The trial court awarded The BOC Group delay damages. It found that The BOC Group did not cause the delay in payment *443of damages and that delay damages would put it in a similar economic position as before the taking.2 On appeal, the Commonwealth Court affirmed the award but vacated the order that interest be paid at the market rate. It remanded for a hearing to determine the applicable interest rate. The Commonwealth Court rejected PennDOT’s argument that delay damages are not recoverable on special damages. It also rejected PennDOT’s argument that The BOC Group was not entitled to delay damages, even if they are recoverable on special damages, because PennDOT never took possession of the condemned property. We granted PennDOT’s petition for allowance of appeal.
Appellate review of a trial court’s decision in an eminent domain matter is limited to a determination of whether the trial court abused its discretion or committed an error of law and whether the findings and conclusions are supported by sufficient evidence. In re Appeal of Waite, 163 Pa. Commw. 283, 288 n. 1, 641 A.2d 25, 27 n. 1, appeal denied, 539 Pa. 657, 651 A.2d 543 (1994).
Under section 611 of the Eminent Domain Code, the recovery of delay damages depends upon whether a condemnee remains in possession of condemned property. The statute states:
The condemnee shall not be entitled to compensation for delay in payment during the period he remains in possession after the condemnation, nor during such period shall a condemnor be entitled to rent or other charges for use and occupancy of the condemned property by the condemnee. Compensation for delay in payment shall, however, be paid at the rate of six per cent per annum from the date of *444relinquishment of possession of the condemned property by the condemnee, or if the condemnation is such that possession is not required to effectuate it, then delay compensation shall be paid from the date of condemnation^]
26 Pa. Stat. § 1-611. Section 611 also states that delay damages are not recoverable on amounts the condemnor has paid the condemnee or has deposited with the court. Id. Delay damages are calculated when a condemnation damages award is paid. Id. The statute concludes:
Provided, however, That no compensation for delay shall be payable with respect to funds paid on account, or by deposit in court, after the date of such payment or deposit. Compensation for delay shall not be included by the viewers or the court or jury on appeal as part of the award of verdict, but shall at the time of payment of the award or judgment be calculated as above and added thereto. There shall be no further or additional payment of interest on the award or verdict.
Id.
Section 611 does not address the issue in this case—whether delay damages are recoverable on special damages. The statute does not distinguish the various kinds of damages recoverable under the Eminent Domain Code. To the contrary, it provides compensation to condemnees for delay in “payment” from the time that they relinquish possession of a condemned property.
The parties stipulated that The BOC Group is a condemnee.3 A tenánt-condemnee is entitled to delay damages from the date it relinquishes possession of a condemned property. Redevelopment Auth. of Philadelphia v. Driscoll, 45 Pa. Commw. 202, 207, 405 A.2d 975, 978 (1979). A tenant’s condemnation damages include special damages, such as losses related to personal property and relocation expenses. See 26 Pa. Stat. § 1-601A (setting forth recoverable special dam*445ages). In light of the purpose of delay damages to provide compensation where a condemnor belatedly pays condemnation damages to a condemnee4 and the rule of strict construction against the Commonwealth,5 we hold that delay damages are recoverable on special damages. The statute does not distinguish between late payment of damages for the loss in value of a condemnee’s property interest and late payment of other kinds of damages. We see no reason to draw such a distinction.
PennDOT relies upon Redevelopment Auth. of Chester v. Swager, 12 Pa. Commw. 437, 316 A.2d 136 (1974) and White v. Redevelopment Auth. of McKeesport, 69 Pa. Commw. 307, 451 A.2d 17 (1982), where contrary to its decision in this case, the Commonwealth Court held that delay damages are not recoverable on special damages. The court reasoned in these cases that section 611 applies “only to condemned property and when and how delay compensation shall be computed on the value of the condemned property.” Swager, 12 Pa. Commw. at 446, 316 A.2d at 140. This is a misreading of the statute. Section 611 does not say that delay damages are computed on the value of the condemned property. Rather, the statute provides that compensation will be paid for delays in payment. It addresses when delay damages begin to accrue and the rate at which they are paid.
PennDOT also argues that The BOC Group is not entitled to delay damages because special damages are set forth in Article VI-A of the Eminent Domain Code and delay damages are contained in Article VI. We disagree. Under Article VI of the Eminent Domain Code, a condemnee is entitled to just compensation for the taking of his property. 26 Pa. Stat. § 1-601. Just compensation is defined as:
the difference between the fair market value of the condemnee’s entire property interest immediately before the *446condemnation and as unaffected thereby and the fair market value of the property interest immediately after such condemnation and as affected thereby, and such other damages as are provided in this code.
Id. § 1-602 (emphasis added). “Other damages” include special damages set forth in Article VI-A. Id., Comment-Joint State Government Comm’n, 1971 Report. Thus, just compensation encompasses special damages. See also Pikur v. Commonwealth, 163 Pa. Commw. 251, 641 A.2d 11 (1994)(stating that just compensation includes special damages).6 Since just compensation includes Article VI and VI-A damages and the purpose of delay damages is to compensate for delays in payment after a taking, we agree with the Commonwealth Court that the allowance of special damages in Article VI-A, as opposed to Article VI, does not preclude recovery of delay damages for their late payment.7
While delay damages are recoverable on late payment of special damages, as discussed above, they only begin to accrue when the condemnee relinquishes possession of the condemned property. In Hughes v. Dep’t of Transportation, 514 Pa. 300, 309-10, 523 A.2d 747, 751-52 (1987), this Court construed the meaning of “possession” in this context. The Court explained that when property is condemned, the Commonwealth has equitable possession with the option to take physical possession. Until it exercises its option, the landown*447er remains in physical possession. The Court held in Hughes that where a declaration of taking deprives a landowner of the full and normal use of his property, as established by the use to which his property was devoted before the declaration, the landowner is no longer in possession under section 611. In such a case, the condemnee may claim delay damages from the date of the declaration of taking. See also Pittsburgh North, Inc. v. Dep’t of Transportation, 514 Pa. 316, 523 A.2d 755 (1987)(where PennDOT’s condemnation did not interfere with the condemnee’s normal use of the property, condemnee was not entitled to delay damages).
PennDOT correctly argues that The BOC Group is not entitled to delay damages because PennDOT never took physical possession of the condemned property and the filing of the declaration of taking did not disrupt the ability to use it. The Stipulation of Facts, upon which the parties agreed that this case would be decided, provides that PennDOT never took possession of the real estate or any machinery, equipment or personal property located therein. It also provides that the landowner had possession of the real estate subject to the declaration of taking. The Stipulation of Facts does not state that The BOC Group was deprived of the normal use of the property after the filing of the declaration of taking. While The BOC Group chose to vacate the property, it fails to explain why it left. We find that PennDOT has met its burden of overcoming the presumption of entitlement to delay damages8 and that, under Hughes and Pittsburgh North, The BOC Group is not entitled to delay damages.
We thus hold that condemnees may recover damages for delays in payment of special damages under the Eminent Domain Code. The BOC Group, however, is not entitled to delay damages since PennDOT never took physical possession of the property and there is no evidence that The BOC Group was deprived of the property’s use. The Commonwealth Court’s decision is thus reversed and its order to remand to *448the trial court to determine the applicable interest rate is vacated. Jurisdiction relinquished.
CAPPY, J., concurs in the result.
ZAPPALA, J., files a concurring opinion in which CASTILLE J., joins.
NEWMAN, J., did not participate in the consideration or decision of this case.