160 A.D. 119

Jeremiah R. Smith, Appellant, v. Thomas H. Cary and Mary F. Cary, Respondents.

Third Department,

January 7, 1914.

Pleading — complaint—foreclosure of mechanic’s lien—allegation of due performance of .builder’s contract — allegation as to architect’s certificate.

A complaint in an action for the foreclosure of a mechanic’s lien which sets out a builder’s contract under which the defendant was to make final payment when the work was completed and accepted by the architect, and alleges pursuant to section 533 of the Code of Civil Procedure that the plaintiff “has duly performed all the conditions of the said contract on his part,” is sufficient.

The general allegation in the language of the Code is broad enough to cover the provision of the contract as to the architect’s certificate or acceptance.

Appeal by the plaintiff, Jeremiah R. Smith, from an interlocutory judgment of the Supreme Court in favor of the defendants, entered in the office of the clerk of the county of Madison on the 21st day of July, 1913, upon the decision of the court rendered after a trial at the Madison Special Term sustaining a demurrer to the complaint.

Joseph Beal, for the appellant.

Coville & Moore [Charles R. Coville of counsel], for the respondents.

Smith, P. J.:

This action was brought for the foreclosure of a mecnamc’s lien. The amended complaint sets out a builder’s contract in which the defendant Thomas H. Gary agreed to pay a certain sum as follows: “One-third when the roofing is completed; one-third when all the materials are on the premises; one-third when the job is completed and accepted by the architect.” The complaint further alleges that the plaintiff did the work and furnished the materials and “has duly performed all the conditions of the said contract on his part.” Section 533 of the Code provides: “In pleading the performance of a condition precedent in a contract, it is not necessary *120to state the facts constituting performance; but the party may state, generally, that he, or the person whom he represents, duly performed all the conditions on his part.” The complaint was demurred to upon the ground that it did not state facts sufficient to. constitute a cause of action, and the learned trial judge sustained the demurrer upon the authority of Conolly v. Hyams (47 App. Div. 592), Weeks v. O’Brien (141 N. Y. 199), Granger Co. v. B.-K. Iron Works (204 id. 218), and “several other authorities” which he does not mention by name. I think that both reason and authority are opposed to the judgment appealed' from. The Conolly case does not seem to be mentioned by the respondents in their points and does not involve any question of pleading. The Weeks case holds merely that a complaint setting out a building contract containing the condition of an architect’s certificate before payment must aver “either generally or specially that the conditions precedent had been performed. ” It appears from Mr. Justice Jenks’ discussion of this case in Fox v. Cowperthwait (60 App. Div. 528, 530) that the complaint in the Weeks case did not “contain any allegation whatever concerning the architect’s certificate, or any general allegation that could refer thereto.” In the case at bar the general allegation in the language of the Oode seems fairly to refer to this matter of the architect’s certificate or acceptance, and consequently the Weeks case is not an authority for the respondents. The complaint in the Granger Co. case apparently contains no reference either specially or in general terms to the condition of the architect’s certificate and cites the Weeks case to the effect that the complaint should aver “either generally or specially that the conditions precedent had been performed.” The only case cited by the respondents which seems to be in point upon the facts is that of Dalzell v. Fahys Watch Case Co. (17 N. Y. Supp. 365), where it was held that section 533 does not apply where the plaintiff specifically sets out in his complaint a condition precedent to be performed by him, and then fails to allege performance of such condition in specific terms. That case was reversed in 138 New York, 285, the Court of Appeals, however,' saying nothing about the holding of the case on the point just mentioned and reversing it on *121other grounds. The case accordingly is a poor authority for the respondents, even though the part of the opinion relied on by them does not appear to have been directly disapproved of by the Court of Appeals. In the case of Rowe v. Gerry (86 App. Div. 349) it was held that where the plaintiff alleged in suing upon a building contract providing for an architect’s certificate that he had duly performed all the conditions of said contract on his part to be performed, he was not entitled thereunder to give evidence excusing non-performance on his part. But Mr. Justice Woodward, in reversing the case because of errors in admitting evidence as to excuses for non-performance, said: “It is not alleged in the complaint that such certificate has been granted,” thus implying that the general allegation of the complaint in the wording of the Code that due performance had been made was not a sufficient allegation. This remark seems purely obiter and was the only thing said on this point in his opinion.

The appellant relies on the Fox case, already mentioned, and Vandegrift v. Bertron (83 App. Div. 548). In the Fox case which was in the Second Department, the supervision and assent of certain parties were necessary and there was an allegation that the plaintiff and the contractor had duly performed all the conditions of the contract. It was held, upon the authority of the Weeks case that this was a sufficient averment of the performance of the conditions precedent, and the judgment of the Special Term overruling a demurrer to the complaint was affirmed. The opinion refers with approval to the pleading given in 1 Abbott’s Forms of Pleading (p. 196), where the note reads: “If the contract provides that plaintiff shall procure an architect’s certificate before defendant shall make payment, this general allegation of performance [i. e., in the wording of the Code] is held sufficient and no special allegation that such certificate was obtained is necessary.” The author cites several cases from other States on this proposition and also the Weeks case. The Vandegrift case was in the Fourth Department, and also holds upon demurrer as regards the condition of an engineer’s acceptance that the plaintiff may allege generally that he has performed all conditions of the contract in the wording of section 533. Neither *122that case nor the Fox case has been overruled, nor do they appear to have been cited upon this particular point. It seems to me that they are both authorities in favor of the appellant’s position, and I think they should be followed in the case at bar.

The respondents argue that section 533 of the Code refers only to conditions which the appellant may duly perform, and. that acceptance by the architect is a condition precedent to be performed by some one else. This seems a most technical distinction. Generally speaking all the conditions of a contract, precedent or otherwise, are to he performed by, or their performance is to he secured by, one party or the other to the contract. One of the two parties to the contract in every case must be specially interested in obtaining the performance of any condition that may in any way be within the power of an outside party to perform. I do not think that the Code provision mentioned intends to allow a party to a contract to allege generally performance when he is the one who actually performs the condition, and not to allow him to plead performance in the same manner when he is vitally interested in obtaining the performance by another, even though the outside party may perform the act. It is commonly said that in builders’ contracts the obtaining or securing of an architect’s acceptance is a condition precedent to payment. At all events it is the builder who is interested in obtaining, and who does obtain when he can, such an acceptance, and consequently it seems to me that the securing of such an acceptance is really a condition precedent to be performed by the builder “on his part,” and so within the fair meaning of section 533 of the Code. I accordingly am of the opinion that paragraph 3 of. the complaint in this action was broad enough to cover, and would fairly be understood as covering, the requirement of the contract as to the architect’s acceptance.

The judgment sustaining the demurrer should be reversed, with costs.

All concurred.

Interlocutory judgment reversed, with costs, and demurrer overruled, with costs, with leave to defendants to withdraw demurrer and answer upon payment of costs.

Smith v. Cary
160 A.D. 119

Case Details

Name
Smith v. Cary
Decision Date
Jan 7, 1914
Citations

160 A.D. 119

Jurisdiction
New York

References

Referencing

Nothing yet... Still searching!

Referenced By

Nothing yet... Still searching!